| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 29 Oct 2024 | Package 1-99% Completed. Power Connection from KSEB is pending. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024 Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 28 Oct 2024 | Package 1-99% Completed. Power Connection from KSEB is pending. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024 Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 25 Oct 2024 | Package 1-99% Completed. Power Connection from KSEB is pending. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024 Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 24 Oct 2024 | Package 1-99% Completed. Power Connection from KSEB is pending. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024 Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 23 Oct 2024 | Package 1-99% Completed. Power Connection from KSEB is pending. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024 Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 22 Oct 2024 | Package 1-99% Completed. Power Connection from KSEB is pending. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024 Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 21 Oct 2024 | Package 1-99% Completed. Power Connection from KSEB is pending. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024 Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 19 Oct 2024 | Package 1-99% Completed. Power Connection from KSEB is pending. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024 Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 18 Oct 2024 | Package 1-99% Completed. Power Connection from KSEB is pending. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024 Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 17 Oct 2024 | Package 1-99% Completed. Power Connection from KSEB is pending. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024 Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 |