Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Aug 2021 Reinforcement work for compound wall started ....Directed contractor to submit revised layout and design .Also addressed corporation Kollam for demarcation of boundary at disputed side Kollam Project HD
25 Aug 2021 .Major components are marked at site at undisputed area. Steel reinforcement works will start on 25.08.2021 for the compound wall. RCC for compound wall is proposed on 26.08.2021. and excavation of Clarifier is proposed on 25.08.2021. Kollam Project HD
24 Aug 2021 .Major components are marked at site at undisputed area. Steel reinforcement works will start on 25.08.2021 for the compound wall. RCC for compound wall is proposed on 26.08.2021. and excavation of Clarifier is proposed on 25.08.2021. Kollam Project HD
18 Aug 2021 Work for the boundary wall foundation pcc and work for site leveling works in progress in undisputed area of land Kollam Project HD
15 Aug 2021 As per the meeting conducted Today( 14.08.2021) by chaired by thesuperintending Engineer & the Executive engineer project Division kollam with contractor, the following points were discussed 1. The letter from Hon. Mayor will be forwarded to the contractor for progressing the work. Contractor assured 1. Survey will be completed by Monday and layout as per actual site will be submitted by Tuesday ( 17.8.2021) 2. Revised working schedule by Wednesday ( 18.8.2021) 3. By the time works upto PCC of compound wall will be completed for all 3 sides of the site. 4. Mix design and steel testing results will be submitted at the earliest. ( RCC can be proceeded with M25 instead of M20 for compound wall as per the mix design already obtained without any delay) 5. Appointment of new experienced engineer , site office, Debries shifting will be done at the earliest 6.Excavation of secondary clarifier will be continued and pipes/ special will be ordered at the earliest. Kollam Project HD
14 Aug 2021 Excavation works for clarifier started.......Set out as per approved layout done at site...part of inlet components, generator room, transformer room, blower room and administrative buildings were inside the disputed area. Directed contractor to realign max. Possible minimum space and to submit for approval Kollam Project HD
09 Aug 2021 Set out as per approved layout done at site...part of inlet components, generator room, transformer room, blower room and administrative buildings were inside the disputed area. Directed contractor to realign max. Possible minimum space and to submit for approval Kollam Project HD
07 Aug 2021 Site leveling works in progress... boundary demarcation yet to be done by revenue & corporation Kollam. Kollam Project HD
05 Aug 2021 As per the meeting with Hon.Mayor kollam, the following directions were issued to Corporation authorities 1. Directed to demarcate the boundaries on 5.08.2021 itself with Taluk surveyor 2. KWA to proceed as per the approved layout drawing and to start with components in undisputed land . EE project , KWA informed the importance of components proposed ( inlet components) at disputed land and boundary demarcation Due to the public protest the boundary demarcation process stopped on 5.08.2021 Kollam Project HD
03 Aug 2021 Work for site leveling in progress...Works for the components as per as per approved drawing may be started only after handing over whole site to KWA.Meeting with Hon..Mayor regarding the issues - site handing over to KWA scheduled on 4.8.2021 2 pm at Kollam corporation. Kollam Project HD