| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 18 Dec 2021 | Clarifier 1 part B earth levelling and Compacting .MBBR IV reinforcement work. Chlorine room lintel bottom form work .Compound wall RR work and plastering.. | Kollam Project HD | |
| 17 Dec 2021 | Clarifier 1 balance area earth excavation and levelling. MBBR IV raft steel work. Compound wall RR work and plastering.Chlorine contact tank earth excavation. | Kollam Project HD | |
| 09 Dec 2021 | Clarifier no.2 - PCC 80% completed, Epoxy coated steel arrived at site, Pipes also arrived. Clarifier no.1 excavation completed and preparing for PCC. MBBR No. IV PCC completed and reinforcement work will start today. Earth shifting in progress for excavating MBBR No.III. For chlorine room and tonner shed- Shuttering and reinforcement works of columns in progress. Compound wall 70 percentage completed | Kollam Project HD | |
| 03 Dec 2021 | work for RCC plinth beam of chlorine room completed. PCC work of Secondary clarifier no.2 restarted and partially completed. Work for compound wall also in progress | Kollam Project HD | |
| 01 Dec 2021 | Decision taken in the Meeting dated 8.11.2021…File No: 1425/A2/2021/KCZMA As per the minutes of meeting dated 8.11.21 The CRZ clearance was issued by KCZMA on 28.04.2012. The CRZ clearance issued will remain valid for a period of 7 years, as per 4.2 (i) h (V) of CRZ notification, and it can be extended by a maximum of three years. The validity of CRZ Clearance will expire on 28.04.2022. | Kollam Project HD | |
| 30 Nov 2021 | Work delayed due to intermittent heavy rain and heavy water seepage. Works upto MBBR PCC no. Iv completed Chlorine room rcc works upto plinth beam bottom completed. Excavation of clarifier 2 completed and 1 partially completed. Compound wall works in undisputed area 80 percent completed | Kollam Project HD | |
| 28 Nov 2021 | Work delayed due to intermittent heavy rain and heavy water seepage. Works upto MBBR PCC no. Iv completed Chlorine room rcc works upto plinth beam bottom completed. Excavation of clarifier 2 completed and 1 partially completed. Compound wall works in undisputed area 80 percent completed. | Kollam Project HD | |
| 14 Nov 2021 | Works for 1.PCC for MBBR tank completed. 2. Secondary clarifier pcc works completed at peripheral portion partially. 3. RCC work of footing for chlorine room completed for all footings. 4. Compound wall work in progress ..Due to heavy rain and material shortage is work is very slow | Kollam Project HD | |
| 06 Nov 2021 | Works for 1. Secondary clarifier pcc works started at peripheral portion 2. RCC work of footing for chlorine room started 3. Compound wall work in progress | Kollam Project HD | |
| 03 Nov 2021 | Works for secondary clarifier no.1 excavation in progress... footing for chlorine room reinforcement work completed...ready for rcc | Kollam Project HD |