| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 30 Dec 2021 | Chlorine contact tank ...PCC work completed..Clarifier no-2-raft shuttering woks in progress..MBBR IV ..Wall reinforcement works in progress..MBBR III ...earth work in progress..Clarifier no 1..PCC works in progress..Compound wall block work and plastering works in progress.. | Kollam Project HD | |
| 29 Dec 2021 | Clarifier no-2- reinforcement work in final stage. MBBR 3 ..earth excavation work in progress..Chlorine contact tank.. earth excavation completed and ready for PCC...MBBR IV ..RCC raft work completed ..Compound wall in progress. | Kollam Project HD | |
| 28 Dec 2021 | Work for MBBR no. IV RCC raft work completed. Clarifier no. 2 - reinforcement work in final stage..MBBR 3 excavation started.. CCT excavation completed and ready for PCC.. Clarifier no. 1 PCC in progress | Kollam Project HD | |
| 24 Dec 2021 | MBBR IV.. reinforcement completed..Chlorine room lintel RCC work...Chlorine contact tank.. PCC work..Clarifier 1..Pipe encasing work in progress..Clarifier 2 ..reinforcement work in progress..Compound wall in progress.. | Kollam Project HD | |
| 23 Dec 2021 | Chlorine contact tank...Excavation work in progress..Chlorine room lintel work in progress....MBBR IV reinforcement completed..Compound wall in progress...Clarifier 2...reinforcement work in progress...Clarifier 1 PCC work in progress.. | Kollam Project HD | |
| 22 Dec 2021 | Clarifier 1 earth levelling,compacting and PCC . Clarifier 2 reinforcement work progress.Chlorine contact tank earth excavation, Chlorine room lintel steel work and form work. Compound wall block work and plastering. | Kollam Project HD | |
| 21 Dec 2021 | Chlorine contact tank excavation and Chlorine room steel work . Clarifier 2 reinforcement work progress. Clarifier 1 sludge trench excavation progress and PCC, Compound wall block work. | Kollam Project HD | |
| 20 Dec 2021 | Chlorine contact tank excavation and Chlorine room lintel form work and reinforcement. Clarifier 2 steel work started. MBBR IV wall reinforcement work, Clarifier 1 sludge trench excavation, Compound wall belt reinforcement and RCC work. | Kollam Project HD | |
| 19 Dec 2021 | Works for Clarifier No.2 ..PCC completed & Pipe inlet and outlet-sludge- laying completed. For Clarifier No.1 - PCC works in progress.. For MBBR IV - Reinforcement works for Raft foundation almost completed and ready for RCC by Tomorrow. For Chlorine room and toner shed - work for lintel beam in progress. | Kollam Project HD | |
| 18 Dec 2021 | Clarifier 1Part B earth levelling and compacting. MBBR IV reinforcement work. Chlorine room lintel bottom form work. Compound wall RR ,belt steel work and shuttering. | Kollam Project HD |