Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 Dec 2021 Chlorine contact tank ...PCC work completed..Clarifier no-2-raft shuttering woks in progress..MBBR IV ..Wall reinforcement works in progress..MBBR III ...earth work in progress..Clarifier no 1..PCC works in progress..Compound wall block work and plastering works in progress.. Kollam Project HD
29 Dec 2021 Clarifier no-2- reinforcement work in final stage. MBBR 3 ..earth excavation work in progress..Chlorine contact tank.. earth excavation completed and ready for PCC...MBBR IV ..RCC raft work completed ..Compound wall in progress. Kollam Project HD
28 Dec 2021 Work for MBBR no. IV RCC raft work completed. Clarifier no. 2 - reinforcement work in final stage..MBBR 3 excavation started.. CCT excavation completed and ready for PCC.. Clarifier no. 1 PCC in progress Kollam Project HD
24 Dec 2021 MBBR IV.. reinforcement completed..Chlorine room lintel RCC work...Chlorine contact tank.. PCC work..Clarifier 1..Pipe encasing work in progress..Clarifier 2 ..reinforcement work in progress..Compound wall in progress.. Kollam Project HD
23 Dec 2021 Chlorine contact tank...Excavation work in progress..Chlorine room lintel work in progress....MBBR IV reinforcement completed..Compound wall in progress...Clarifier 2...reinforcement work in progress...Clarifier 1 PCC work in progress.. Kollam Project HD
22 Dec 2021 Clarifier 1 earth levelling,compacting and PCC . Clarifier 2 reinforcement work progress.Chlorine contact tank earth excavation, Chlorine room lintel steel work and form work. Compound wall block work and plastering. Kollam Project HD
21 Dec 2021 Chlorine contact tank excavation and Chlorine room steel work . Clarifier 2 reinforcement work progress. Clarifier 1 sludge trench excavation progress and PCC, Compound wall block work. Kollam Project HD
20 Dec 2021 Chlorine contact tank excavation and Chlorine room lintel form work and reinforcement. Clarifier 2 steel work started. MBBR IV wall reinforcement work, Clarifier 1 sludge trench excavation, Compound wall belt reinforcement and RCC work. Kollam Project HD
19 Dec 2021 Works for Clarifier No.2 ..PCC completed & Pipe inlet and outlet-sludge- laying completed. For Clarifier No.1 - PCC works in progress.. For MBBR IV - Reinforcement works for Raft foundation almost completed and ready for RCC by Tomorrow. For Chlorine room and toner shed - work for lintel beam in progress. Kollam Project HD
18 Dec 2021 Clarifier 1Part B earth levelling and compacting. MBBR IV reinforcement work. Chlorine room lintel bottom form work. Compound wall RR ,belt steel work and shuttering. Kollam Project HD