| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 16 Jul 2021 | No work due to heavy rain.. | Kollam Project HD | |
| 15 Jul 2021 | Work for the construction of compound wall excavation in the undisputed area started on 15.07.2021...other areas demarcation to be done and official land handing over pending | Kollam Project HD | |
| 14 Jul 2021 | As per meeting with Hon.Mayor , Kollam the following decisions were taken. 1. Official land handed over will be done by corporation after cutting trees in the disputed land by corporation itself to KWA 2. Directed to start the works for the compound wall in the front side ( road side only) and directed to do demarcation urgently for other area by Taluk surveyor... 4. Details of the disputed land and purampoke will be handed over to KWA immediately after verification .... 5. Directed to proceed with approved layout and problems related to land & other hurdles will be skrrout by the corporation urgently and will be handed over to KWA | Kollam Project HD | |
| 13 Jul 2021 | No work today....work for tree cutting stopped by the disputed owner and stopped at the disputed area..Meeting with the Hon.Mayor at 2.30 pm to discuss the following issues ...... 1. For boundary demarcation issue / land shortage issues:. ... ..Hon. Mayor directed to start works for compound wall immediately after handing over survey drawing and land extend details from Taluk office to KWA as per approved layout after cutting trees in the disputed land .Also if any issues arises during compound wall works shall be taken care of Corporation and directed to proceed with the approved layout ...........2. for purampoke land, it will be handed over to KWA immediately since it is vested with Corporation Kollam.......3. A meeting is also scheduled on 14.07.2021 for discussing further decision of inauguration and other issue | Kollam Project HD | |
| 12 Jul 2021 | work for tree cutting stopped by the disputed owner and stopped at the disputed area..Meeting with the Hon.Mayor at 2.30 pm ( 08.07.2021) to discuss the following issues ...... 1. For boundary demarcation issue / land shortage issues:. ... ..Hon. Mayor directed to start works for compound wall immediately after handing over survey drawing and land extend details from Taluk office to KWA as per approved layout after cutting trees in the disputed land .Also if any issues arises during compound wall works shall be taken care of Corporation and directed to proceed with the approved layout ...........2. for purampoke land, it will be handed over to KWA immediately since it is vested with Corporation Kollam.......3. A meeting is also scheduled on 14.07.2021 for discussing further decision of inauguration and other issues | Kollam Project HD | |
| 10 Jul 2021 | No work due to heavy rain.....Meeting with the Hon.Mayor at 2.30 pm to discuss the following issues ...... 1. For boundary demarcation issue / land shortage issues:. ... ..Hon. Mayor directed to start works for compound wall immediately after handing over survey drawing and land extend details from Taluk office to KWA as per approved layout after cutting trees in the disputed land .Also if any issues arises during compound wall works shall be taken care of Corporation and directed to proceed with the approved layout ...........2. for purampoke land, it will be handed over to KWA immediately since it is vested with Corporation Kollam.......3. A meeting is also scheduled on 14.07.2021 for discussing further decision of inauguration and other issues | Kollam Project HD | |
| 08 Jul 2021 | Meeting with the Hon.Mayor at 2.30 pm to discuss the following issues ...... 1. For boundary demarcation issue / land shortage issues:. ... ..Hon. Mayor directed to start works for compound wall immediately after handing over survey drawing and land extend details from Taluk office to KWA as per approved layout after cutting trees in the disputed land .Also if any issues arises during compound wall works shall be taken care of Corporation and directed to proceed with the approved layout ...........2. for purampoke land, it will be handed over to KWA immediately since it is vested with Corporation Kollam.......3. A meeting is also scheduled on 13.07.2021 for discussing further decision of inauguration and other issues | Kollam Project HD | |
| 07 Jul 2021 | A meeting with Hon. Mayor is scheduled at 2pm for discussing the issues related land handing over at corporation , kollam on 08.07.2021...Tree cutting completed except in the disputed land. On 30 June 2021... Boundary demarcation partially done by Taluk surveyor and corporation Authority... During demarcation it is found that The land boundary demarcated earlier by the corporation was not with the Corporation Kollam as the some of the areas are with private owners as per the revenue department.So the land is insufficient as per the approved layout. The matter was intimated to Kollam corporation for handing over balance land | Kollam Project HD | |
| 06 Jul 2021 | On 30 June 2021... Boundary demarcation partially done by Taluk surveyor and corporation Authority... During demarcation it is found that 1. The land boundary demarcated earlier by the corporation was not with the Corporation Kollam as the some of the areas are with private owners as per the revenue department.So the land is insufficient as per the approved layout 2. Final sketch and stretch is to be handed over to KWA 3. Already addressed Corporation Kollam for handing over balance extend of land with land under thirikadavoor gp Work for tree cutting and site leveling in progress | Kollam Project HD | |
| 06 Jul 2021 | On 30 June 2021... Boundary demarcation partially done by Taluk surveyor and corporation Authority... During demarcation it is found that 1. The land boundary demarcated earlier by the corporation was not with the Corporation Kollam as the some of the areas are with private owners as per the revenue department.So the land is insufficient as per the approved layout 2. Final sketch and stretch is to be handed over to KWA 3. Already addressed Corporation Kollam for handing over balance extend of land with land under thirikadavoor gp Work for tree cutting and site leveling in progress | Kollam Project HD |