30 Oct 2021 work for PCC of MBBR tank IV completed on 30.10.21.. The work for footing of Chlorine room started.. The work for compound wall -Plinth beam above piles completed..Block work in progress.. Secondary Clarifier preparation for PCC work in progress.. Delayed due to intermittent rains Kollam Project HD
27 Oct 2021 Work for MBBR tank pcc scheduled 27.10.2021 postponed due to rain..works for compound wall in progress...pile cap shuttering and reinforcement works in progress... excavation for footing of chlorination room and tonnershed started Kollam Project HD
23 Oct 2021 Works for compound wall in progress and works for excavation is not possible due to rain Kollam Project HD
22 Oct 2021 Work for 1.excavation of MBBR completed, 2.works for compound wall piling completed 3. PCC of secondary clarifier 2 and MBBR is pending due to heavy rain 4. Revised layout approved from kollam Corporation and WASCON Kollam Project HD
15 Oct 2021 Work for the excavation of MBBR no.iv also completed..pcc postponed for secondary clarifier no.2 due to heavy rain Kollam Project HD
12 Oct 2021 Work in progress..very slow due to heavy rain Kollam Project HD
10 Oct 2021 No work due to heavy rain...pcc work postponed Kollam Project HD
09 Oct 2021 PCC work for the centre portion of clarifier completed and balance portion proposed postponed due to heavy rain... excavation of MBBR iv and compound wall worksnin progress Kollam Project HD
06 Oct 2021 Works for excavation works for MBBR iv in progress, compound wall in progress Kollam Project HD
02 Oct 2021 Works for excavation of secondary clarifier in progress no.1 and no.2 completed... boundary wall plastering started at one side Kollam Project HD