| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Jul 2021 | On 30 June 2021... Boundary demarcation partially done by Taluk surveyor and corporation Authority... During demarcation it is found that 1. The land boundary demarcated earlier by the corporation was not with the Corporation Kollam as the some of the areas are with private owners as per the revenue department.So the land is insufficient as per the approved layout 2. Final sketch and stretch is to be handed over to KWA 3. Already addressed Corporation Kollam for handing over balance extend of land with land under thirikadavoor gp Work for tree cutting and site leveling in progress | Kollam Project HD | |
| 02 Jul 2021 | On 30 June 2021... Boundary demarcation partially done by Taluk surveyor and corporation Authority... During demarcation it is found that 1. The land boundary demarcated earlier by the corporation was not with the Corporation Kollam as the some of the areas are with private owners as per the revenue department.So the land is insufficient as per the approved layout 2. Final sketch and stretch is to be handed over to KWA 3. Already addressed Corporation Kollam for handing over balance extend of land with land under thirikadavoor gp Work for tree cutting and site leveling in progress | Kollam Project HD | |
| 30 Jun 2021 | Tree cutting works in progress...Boundary fixation works proposed on 30.6.2021 by Taluk surveyor and corporation Authority...for shifting kseb post ...demand of Rs. 1.9lakhs submitted to Kseb on 29.06.21 | Kollam Project HD | |
| 29 Jun 2021 | Tree cutting works by corporation Kollam in progress 95 percent completed...Boundary fixation work at one side is pending and is proposed demarcation on 30.06.2021 by Taluk surveyor & Corporation authorities | Kollam Project HD | |
| 24 Jun 2021 | Tree cutting works by corporation Kollam in progress 85 percent completed... submitted structural designs of all major components approved except sludge holding tank( returned for resubmitting).All other drawings submitted for approval at WASCON.. Directed contractor to submit revised schedule.. Boundary fixation work at one side is pending | Kollam Project HD | |
| 22 Jun 2021 | Tree cutting works by corporation Kollam in progress 60 percent completed... submitted structural designs of all major components approved except sludge holding tank( returned for resubmitting).All other drawings submitted for approval at WASCON.. Directed contractor to submit revised schedule.. Boundary fixation work at one side is pending | Kollam Project HD | |
| 20 Jun 2021 | The work for tree cutting is arranged on 21.06.2021 with police protection by Corporation Kollam | Kollam Project HD | |
| 19 Jun 2021 | 2021 Requested corporation for arranging police protection for tree cutting and Kollam Corporation authorities assured to represent the same to concerned police officers today itself. | Kollam Project HD | |
| 16 Jun 2021 | Requested corporation for arranging police protection for tree cutting and Kollam Corporation authorities assured to represent the same to concerned police officers today itself. | Kollam Project HD | |
| 16 Jun 2021 | Requested corporation for arranging police protection for tree cutting and Kollam Corporation authorities assured to represent the same to concerned police officers today itself. Tree cutting proposed on 4.06.2021 postponed as the Dist. Collector Kollam , ACP and the Hon. Mayor recommended and directed for a new date after lockdown in view of GO. (Rt) No. 455/2021/DMD dated 03.06.2021 | Kollam Project HD |