Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 May 2021 The Corporation has informed that they will be able to provide police protection for the works on 11.05.2021 but postponed due to COVID 19 lock down restrictions by GOK. No Works started due to the above Kollam Project HD
13 May 2021 The Corporation has informed that they will be able to provide police protection for the works on 11.05.2021 but postponed due to COVID 19 lock down restrictions by GOK. No Works started due to the above Kollam Project HD
10 May 2021 On 03.05.2021 the Corporation has informed me that they will be able to provide police protection for the works on 11.05.2021 and instructed contractor to make all arrangements for commencing the works. Due to lockdown restrictions the work may be postponed Kollam Project HD
05 May 2021 The corporation later instructed to go ahead with the works on 03 May 2021 and promised that protection from the police will be made available for the works. But on 02 May 2021 the officials from Corporation informed to postpone the works as Police Dept is not in a position to provide the protection as they are engaged with a busy schedule/ COVID Duty. Finally, on 03.05.2021 the Corporation has informed me that they will be able to provide police protection for the works on 11.05.2021 and instructed contractor to make all arrangements for commencing the works. Kollam Project HD
05 May 2021 The Municipal Corporation of Kollam has assigned the works of tree cutting and removing the wood from the construction site for Sewage Treatment Plant for Kollam Corporation at Kureepuzha vide their letter No. R10/H3/12/2021 dated 26.04.2021. Accordingly, on 27.04.2021 , the concerned contractor engaged manpower to cut the trees from the site and started our work. But residents in the locality gathered at the site and objected to our works and finally as per instruction of Corporation authorities we abandoned the works owing to protests from them. Kollam Project HD
05 May 2021 The Municipal Corporation of Kollam has assigned the works of tree cutting and removing the wood from the construction site for Sewage Treatment Plant for Kollam Corporation at Kureepuzha vide their letter No. R10/H3/12/2021 dated 26.04.2021. Accordingly, on 27.04.2021 I engaged my manpower to cut the trees from the site and started the work. But residents in the locality gathered at the site and objected to our works and finally as per instruction of Corporation authorities & stopped the works owing to protests from them. Finally, on 03.05.2021 the Corporation & police authorities informed that they will be able to provide police protection for the works on 11.05.2021 Kollam Project HD
29 Apr 2021 Due to public protest work temporarily stopped.Land not handed over by Corporation Kollam Project HD
23 Apr 2021 Demand notice given to remit the negogiated amount...to the contractor.....on 23.04.2021......19/04/2021 Counsel meeting constituted on 19.04.2021 and the negotiated amount approved for tree cutting..work order to be issued from corporation kollam.... structural design of other components submitted Kollam Project HD
20 Apr 2021 Work in progress | 2% Completed | 19/04/2021 Counsel meeting constituted on 19.04.2021 and the negotiated amount approved for tree cutting..work order to be issued from corporation kollam.... structural design of other components submitted... Kollam Project HD
19 Apr 2021 Counsel meeting constituted on 19.04.2021 and the negotiated amount approved for tree cutting..work order to be issued from corporation kollam Kollam Project HD