| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 31 Jul 2021 | Site leveling works and compound wall excavation & PCC works in progress at undisputed portions..But works for the components as per approved drawing may be started only after handing over whole site from corporation with boundary demarcation | Kollam Project HD | |
| 30 Jul 2021 | Site leveling works and compound wall excavation & PCC works in progress at undisputed portions..But works for the components as per approved drawing may be started only after handing over whole site from corporation with boundary demarcation | Kollam Project HD | |
| 28 Jul 2021 | Work for PCC of STP compound wall at a portion ( front side near road) for 47 m completed. | Kollam Project HD | |
| 27 Jul 2021 | Site leveling works and compound wall excavation in progress...Boundary demarcation and official handing over of site is still pending by corporation and Taluk office for starting the work in full swing | Kollam Project HD | |
| 25 Jul 2021 | .Boundary demarcation and official handing over of site may be done by corporation and Taluk office for starting the work in full swing | Kollam Project HD | |
| 24 Jul 2021 | Site leveling in progress..Boundary demarcation and official handing over of site may be done for starting the work in full swing | Kollam Project HD | |
| 22 Jul 2021 | Work for site Clearing work in progress and works for boundary excavation in progress. Protest from the public was there and they stopped RR lorry to the work site...Later police managed the situation..the work for compound wall excavation in progress at undisputed area | Kollam Project HD | |
| 21 Jul 2021 | Work for the construction of compound wall excavation in the undisputed area started on 15.07.2021..site leveing in progress.other areas demarcation to be done and official land handing over pending | Kollam Project HD | |
| 19 Jul 2021 | Site clearance work in progress...in the undisputed area..other areas demarcation to be done and land handing over to KWA to be done | Kollam Project HD | |
| 17 Jul 2021 | Site clearance work in progress...in the undisputed area..other areas demarcation to be done and land handing over to KWA to be done | Kollam Project HD |