Status Date |
Overall Project Status |
Project Officer |
Contact |
09 Jan 2024 |
55.42 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - finishing work completed. Compound wall completed, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -281 & HTC-474/2735 completed |
Palakkad Proj AE 3 |
|
08 Jan 2024 |
55.42 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - finishing work completed. Compound wall completed, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -281 & HTC-474/2735 completed |
Palakkad Proj AE 3 |
|
06 Jan 2024 |
55.25 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - finishing work completed. Compound wall completed, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -281 & HTC-474/2735 completed |
Palakkad Proj AE 3 |
|
05 Jan 2024 |
55.25 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - finishing work completed. Compound wall completed, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -281 & HTC-474/2735 completed |
Palakkad Proj AE 3 |
|
04 Jan 2024 |
2023 54.13 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing completed, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -276 & HTC-479/2735 completed |
Palakkad Proj AE 3 |
|
04 Jan 2024 |
2023 54.13 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing completed, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -276 & HTC-479/2735 completed |
Palakkad Proj AE 3 |
|
04 Jan 2024 |
54.13 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing completed, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -276 & HTC-479/2735 completed |
Palakkad Proj AE 3 |
|
03 Jan 2024 |
2023 54.13 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing completed, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -276 & HTC-479/2735 completed |
Palakkad Proj AE 3 |
|
03 Jan 2024 |
2023 54.13 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing completed, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -276 & HTC-479/2735 completed |
Palakkad Proj AE 3 |
|
03 Jan 2024 |
2023 54.13 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing completed, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -276 & HTC-479/2735 completed |
Palakkad Proj AE 3 |
|