Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
09 Jan 2024 55.42 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - finishing work completed. Compound wall completed, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -281 & HTC-474/2735 completed Palakkad Proj AE 3
08 Jan 2024 55.42 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - finishing work completed. Compound wall completed, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -281 & HTC-474/2735 completed Palakkad Proj AE 3
06 Jan 2024 55.25 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - finishing work completed. Compound wall completed, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -281 & HTC-474/2735 completed Palakkad Proj AE 3
05 Jan 2024 55.25 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - finishing work completed. Compound wall completed, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -281 & HTC-474/2735 completed Palakkad Proj AE 3
04 Jan 2024 2023 54.13 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing completed, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -276 & HTC-479/2735 completed Palakkad Proj AE 3
04 Jan 2024 2023 54.13 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing completed, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -276 & HTC-479/2735 completed Palakkad Proj AE 3
04 Jan 2024 54.13 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing completed, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -276 & HTC-479/2735 completed Palakkad Proj AE 3
03 Jan 2024 2023 54.13 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing completed, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -276 & HTC-479/2735 completed Palakkad Proj AE 3
03 Jan 2024 2023 54.13 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing completed, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -276 & HTC-479/2735 completed Palakkad Proj AE 3
03 Jan 2024 2023 54.13 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing completed, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -276 & HTC-479/2735 completed Palakkad Proj AE 3