Status Date Overall Project Status Project Officer Contact
19 Mar 2024 61.505/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Tank site :Reinforcement work for valve chamber - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. Total connection completed -830nos(327 FHTC & 503 HTC) Palakkad Project Dn AE
18 Mar 2024 61.457/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Tank site :Reinforcement work for valve chamber - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. Total connection completed -829nos(326 FHTC & 503 HTC) Palakkad Project Dn AE
16 Mar 2024 61.457/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Tank site :Reinforcement work for valve chamber - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. Total connection completed -829nos(326 FHTC & 503 HTC) Palakkad Project Dn AE
15 Mar 2024 13 Mar 2024 61.384/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Tank site : PCC laying for 250mm Sluice valve chamber - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. Total connection completed -829nos(326 FHTC & 503 HTC) Palakkad Proj AE 3
14 Mar 2024 13 Mar 2024 61.221/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Tank site : PCC laying for 250mm Sluice valve chamber - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. Total connection completed -829nos(326 FHTC & 503 HTC) Palakkad Proj AE 3
13 Mar 2024 61.118/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Tank site : PCC laying for 250mm Sluice valve chamber - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. Total connection completed -825nos(322 FHTC & 503 HTC) Palakkad Proj AE 3
05 Mar 2024 60.90/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Site - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. Total connection completed -822nos(313 FHTC & 509 HTC) Palakkad Project Dn AE
24 Feb 2024 59.20/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Site - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -310& HTC-512/2735 completed Palakkad Project Dn EE
12 Feb 2024 59.20/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Site - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -303& HTC-509/2735 completed. Palakkad Project Dn EE
09 Feb 2024 59/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Site - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -303& HTC-507/2735 completed. Palakkad Project Dn EE