Status Date |
Overall Project Status |
Project Officer |
Contact |
07 Feb 2024 |
58.80/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Site - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -297& HTC-509/2735 completed. |
Palakkad Proj Dn AE 4 |
|
05 Feb 2024 |
57.80/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Site - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -290 & HTC-508/2735 completed. |
Palakkad Proj Dn AE 4 |
|
02 Feb 2024 |
57.80/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Site - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -288 & HTC-508/2735 completed. |
Palakkad Proj Dn AE 4 |
|
31 Jan 2024 |
57.67/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Site - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -287 & HTC-507/2735 completed. |
Palakkad Proj AE 3 |
|
30 Jan 2024 |
57.67/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Site - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -287 & HTC-507/2735 completed.
|
Palakkad Proj AE 3 |
|
30 Jan 2024 |
31.48/91.30 km completed. Remaining PVC, HDPE & DI laying progressing, 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress.
|
Palakkad Proj AE 3 |
|
29 Jan 2024 |
57.55/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Site - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -287 & HTC-507/2735 completed.
|
Palakkad Proj AE 3 |
|
27 Jan 2024 |
57.49/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Site - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -287 & HTC-502/2735 completed.
|
Palakkad Proj AE 3 |
|
25 Jan 2024 |
57.26/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Site - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -287 & HTC-502/2735 completed.
|
Palakkad Proj AE 3 |
|
24 Jan 2024 |
57.08/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Site - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -287 & HTC-500/2735 completed.
|
Palakkad Proj AE 3 |
|