Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
20 Dec 2023 53.52 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -271 & HTC-472/2735 completed Palakkad Proj AE 3
19 Dec 2023 53.40/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -271 & HTC-472/2735 completed Palakkad Proj AE 3
18 Dec 2023 53.40/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -271 & HTC-472/2735 completed Palakkad Proj AE 3
16 Dec 2023 52.99 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -265 & HTC-478/2735 completed Palakkad Proj AE 3
15 Dec 2023 52.99 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -265 & HTC-478/2735 completed Palakkad Proj AE 3
14 Dec 2023 52.89 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -265 & HTC-478/2735 completed Palakkad Proj AE 3
13 Dec 2023 52.89 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -265 & HTC-478/2735 completed Palakkad Proj AE 3
12 Dec 2023 52.69 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -265 & HTC-476/2735 completed Palakkad Proj AE 3
11 Dec 2023 52.69 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -265 & HTC-476/2735 completed Palakkad Proj AE 3
08 Dec 2023 52.50 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -265 & HTC-472/2735 completed Palakkad Proj AE 3