Status Date |
Overall Project Status |
Project Officer |
Contact |
20 Dec 2023 |
53.52 /70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -271 & HTC-472/2735 completed
|
Palakkad Proj AE 3 |
|
19 Dec 2023 |
53.40/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -271 & HTC-472/2735 completed
|
Palakkad Proj AE 3 |
|
18 Dec 2023 |
53.40/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -271 & HTC-472/2735 completed
|
Palakkad Proj AE 3 |
|
16 Dec 2023 |
52.99 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -265 & HTC-478/2735 completed
|
Palakkad Proj AE 3 |
|
15 Dec 2023 |
52.99 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -265 & HTC-478/2735 completed |
Palakkad Proj AE 3 |
|
14 Dec 2023 |
52.89 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -265 & HTC-478/2735 completed
|
Palakkad Proj AE 3 |
|
13 Dec 2023 |
52.89 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -265 & HTC-478/2735 completed
|
Palakkad Proj AE 3 |
|
12 Dec 2023 |
52.69 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -265 & HTC-476/2735 completed
|
Palakkad Proj AE 3 |
|
11 Dec 2023 |
52.69 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall white washing on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -265 & HTC-476/2735 completed
|
Palakkad Proj AE 3 |
|
08 Dec 2023 |
52.50 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall
white washing on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. FHTC -265 & HTC-472/2735 completed |
Palakkad Proj AE 3 |
|