JJM-2020-21- Providing FHTC's in the uncovered areas of Thachampara Panchayath, Palakkad, District- Phase-II
Project |
JJM-2020-21- Providing FHTC's in the uncovered areas of Thachampara Panchayath, Palakkad, District- Phase-II |
Project Code |
PKDJJM10204490 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Providing FHTC's in the uncovered areas of Thachampara Panchayath, Palakkad, District- Phase-II |
Status |
On-going |
District |
Palakkad |
Executing Office |
Palakkad Project Dn |
AS Amount (Rs) |
167000000
|
AS Number |
GO(Rt) No. 777/2020/WRD |
TS Amount (Rs) |
139300000 |
TS Number |
TS/2021-2022/2022/2401 |
Total Bill Submitted (Rs) |
99671642 |
Total Bill Paid (Rs) |
55180016 |
Population Benefitted |
26462 |
Capacity in MLD |
21.00 |
Actual Project Completion Date |
31 Jul 2024 |
Coverage |
Karakurissi GP |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM-2020-21- Providing FHTC's in the uncovered areas of Thachampara Panchayath, Palakkad, District- Phase-II |
Project Division Palakkad |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
26 Jun 2024 |
63.346.0/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Road restoration works on going.Total connection completed - 919 Nos. (367 FHTC + 552 HTC) & Primary Geo Tagg Completed -894 Nos. (367 FHTC + 527 HTC) |
Palakkad Proj AE 3 |
|
25 Jun 2024 |
63.346.0/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Road restoration works on going.Total connection completed - 919 Nos. (367 FHTC + 552 HTC) & Primary Geo Tagg Completed -894 Nos. (367 FHTC + 527 HTC) |
Palakkad Proj AE 3 |
|
24 Jun 2024 |
63.346.0/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Road restoration works on going.Total connection completed - 919 Nos. (367 FHTC + 552 HTC) & Primary Geo Tagg Completed -894 Nos. (367 FHTC + 527 HTC) |
Palakkad Proj AE 3 |
|
22 Jun 2024 |
63.346.0/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Road restoration works on going.Total connection completed -919 Nos. (367 FHTC + 552 HTC) & Primary Geo Tagg Completed -894 Nos. (367 FHTC + 527 HTC) |
Palakkad Proj AE 3 |
|
20 Jun 2024 |
63.346.0/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Road restoration works on going.Total connection completed -919 Nos. (367 FHTC + 552 HTC) & Primary Geo Tagg Completed -894 Nos. (367 FHTC + 527 HTC) |
Palakkad Proj AE 3 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
01/10/2022 |
Scheduled date of Completion of the Project |
30 Sep 2023 |
Expected date of Completion |
31/12/2023 |
Processing Dates
AS Date |
24 Dec 2020 |
TS Date |
25 Jan 2022 |