Status Date |
Overall Project Status |
Project Officer |
Contact |
02 Apr 2024 |
62.391/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Tank site :PCC laying & RCC work for valve chamber.Side wall concreting for valve chamber at tank site.Reinforcement work for valve chamber - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. Total connection completed -841nos(337 FHTC & 504 HTC) ,geo tagging 815(335 FHTC + 480 HTC). |
Palakkad Proj AE 3 |
|
01 Apr 2024 |
62.305/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Tank site :PCC laying & RCC work for valve chamber.Side wall concreting for valve chamber at tank site.Reinforcement work for valve chamber - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. Total connection completed -841nos(337 FHTC & 504 HTC) ,geo tagging 815(335 FHTC + 480 HTC). |
Palakkad Proj AE 3 |
|
30 Mar 2024 |
62.269/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Tank site :Side wall concreting for valve chamber at tank site.Reinforcement work for valve chamber - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. Total connection completed -836nos(332 FHTC & 504 HTC) ,geo tagging 811(331 FHTC + 480 HTC). |
Palakkad Proj AE 3 |
|
27 Mar 2024 |
61.9263/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Tank site :Side wall cocreting for valve chamber at tank site.Reinforcement work for valve chamber - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. Total connection completed -834nos(330 FHTC & 504 HTC) ,geo tagging 810(330 FHTC + 480 HTC). |
Palakkad Proj AE 3 |
|
26 Mar 2024 |
61.812/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Tank site :Side wall cocreting for valve chamber at tank site.Reinforcement work for valve chamber - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. Total connection completed -834nos(330 FHTC & 504 HTC) ,geo tagging 810(330 FHTC + 480 HTC). |
Palakkad Proj AE 3 |
|
25 Mar 2024 |
61.773/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Tank site :Reinforcement work for valve chamber - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. Total connection completed -833nos(330 FHTC & 503 HTC) ,geo tagging 810(330 FHTC + 480 HTC). |
Palakkad Proj AE 3 |
|
23 Mar 2024 |
61.691/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Tank site :Reinforcement work for valve chamber - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. Total connection completed -832nos(330 FHTC & 502 HTC) ,geo tagging 810(330 FHTC + 480 HTC). |
Palakkad Proj AE 3 |
|
22 Mar 2024 |
61.580/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Tank site :Reinforcement work for valve chamber - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. Total connection completed -832nos(330 FHTC & 502 HTC) ,geo tagging 810(330 FHTC + 480 HTC) |
Palakkad Proj AE 3 |
|
21 Mar 2024 |
61.567/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Tank site :Reinforcement work for valve chamber - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. Total connection completed -832nos(330 FHTC & 502 HTC) ,geo tagging 807(328 FHTC + 479 HTC) |
Palakkad Proj AE 3 |
|
20 Mar 2024 |
61.523/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. 2 LL GLSR Tank site :Reinforcement work for valve chamber - plastering work completed, Pumping main from glsr 90% completed & valve fixing work completed.Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road) progressing. Total connection completed -832nos(329 FHTC & 503 HTC) |
Palakkad Project Dn AE |
|