Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Jun 2024 | 63.346.0/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Road restoration works on going.Total connection completed - 919 Nos. (367 FHTC + 552 HTC) & Primary Geo Tagg Completed -894 Nos. (367 FHTC + 527 HTC) | Palakkad Proj AE 3 | |
25 Jun 2024 | 63.346.0/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Road restoration works on going.Total connection completed - 919 Nos. (367 FHTC + 552 HTC) & Primary Geo Tagg Completed -894 Nos. (367 FHTC + 527 HTC) | Palakkad Proj AE 3 | |
24 Jun 2024 | 63.346.0/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Road restoration works on going.Total connection completed - 919 Nos. (367 FHTC + 552 HTC) & Primary Geo Tagg Completed -894 Nos. (367 FHTC + 527 HTC) | Palakkad Proj AE 3 | |
22 Jun 2024 | 63.346.0/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Road restoration works on going.Total connection completed -919 Nos. (367 FHTC + 552 HTC) & Primary Geo Tagg Completed -894 Nos. (367 FHTC + 527 HTC) | Palakkad Proj AE 3 | |
20 Jun 2024 | 63.346.0/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Road restoration works on going.Total connection completed -919 Nos. (367 FHTC + 552 HTC) & Primary Geo Tagg Completed -894 Nos. (367 FHTC + 527 HTC) | Palakkad Proj AE 3 | |
18 Jun 2024 | 63.346.0/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Road restoration works on going.Total connection completed -9916 Nos. (367 FHTC + 549 HTC) & Primary Geo Tagg Completed - 892 Nos. (367 FHTC + 525 HTC) . | Palakkad Proj AE 3 | |
14 Jun 2024 | 63.346.0/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Road restoration works on going.Total connection completed -911 Nos. (365 FHTC + 546 HTC) & Primary Geo Tagg Completed - 890 Nos. (365 FHTC + 525 HTC) | Palakkad Proj AE 3 | |
14 Jun 2024 | 63.346.0/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Road restoration works on going.Total connection completed -911 Nos. (365 FHTC + 546 HTC) & Primary Geo Tagg Completed - 890 Nos. (365 FHTC + 525 HTC) | Palakkad Proj AE 3 | |
12 Jun 2024 | 63.346.0/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Road restoration works on going.Total connection completed -909 Nos. (363 FHTC + 546 HTC) & Primary Geo Tagg Completed - 888 Nos. (363 FHTC + 525 HTC) | Palakkad Proj AE 3 | |
10 Jun 2024 | 63.346.0/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Road restoration works on going.Total connection completed -906 Nos. (363 FHTC + 543 HTC) & Primary Geo Tagg Completed - 885 Nos. (363 FHTC + 522 HTC) | Palakkad Proj AE 3 |