Status Date Overall Project Status Project Officer Contact
07 Dec 2023 52.41 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site - tank roof slab side plastering completed & inside waterproof coating applying on going. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -265 & HTC-459/2735 completed Palakkad Proj AE 3
06 Dec 2023 52.03 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -265 & HTC-459/2735 completed Palakkad Proj AE 3
05 Dec 2023 52.03 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -265 & HTC-459/2735 completed Palakkad Proj AE 3
04 Dec 2023 52.03 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -265 & HTC-459/2735 completed Palakkad Proj AE 3
02 Dec 2023 52.03 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -265 & HTC-459/2735 completed Palakkad Proj AE 3
01 Dec 2023 52.03 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -265 & HTC-459/2735 completed Palakkad Proj AE 3
30 Nov 2023 51.23Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -254 & HTC-470/2735 completed Palakkad Proj AE 3
29 Nov 2023 51.23Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -254 & HTC-470/2735 completed Palakkad Proj AE 3
28 Nov 2023 51.09 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -240 & HTC-474/2735 completed Palakkad Proj AE 3
27 Nov 2023 50.91 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -240 & HTC-474/2735 completed Palakkad Proj AE 3