Status Date |
Overall Project Status |
Project Officer |
Contact |
14 Nov 2023 |
49.00 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -220 & HTC-474/2735 completed. |
Palakkad Proj AE 3 |
|
13 Nov 2023 |
48.82 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -220 & HTC-474/2735 completed.
|
Palakkad Proj AE 3 |
|
10 Nov 2023 |
48.69 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -220 & HTC-473/2735 completed.
|
Palakkad Proj AE 3 |
|
09 Nov 2023 |
48.61 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -220 & HTC-473/2735 completed. |
Palakkad Proj AE 3 |
|
08 Nov 2023 |
48.61 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -220 & HTC-473/2735 completed. |
Palakkad Proj AE 3 |
|
07 Nov 2023 |
48.38 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -220 & HTC-471/2735 completed.
|
Palakkad Proj AE 3 |
|
06 Nov 2023 |
48.13 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -179 & HTC-449/2735 completed.
|
Palakkad Proj AE 3 |
|
04 Nov 2023 |
48.13 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -179 & HTC-449/2735 completed.
|
Palakkad Proj AE 3 |
|
03 Nov 2023 |
48.00 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -179 & HTC-449/2735 completed.
|
Palakkad Proj AE 3 |
|
02 Nov 2023 |
47.92 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -179 & HTC-449/2735 completed. |
Palakkad Proj AE 3 |
|