Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Nov 2023 49.00 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -220 & HTC-474/2735 completed. Palakkad Proj AE 3
13 Nov 2023 48.82 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -220 & HTC-474/2735 completed. Palakkad Proj AE 3
10 Nov 2023 48.69 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -220 & HTC-473/2735 completed. Palakkad Proj AE 3
09 Nov 2023 48.61 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -220 & HTC-473/2735 completed. Palakkad Proj AE 3
08 Nov 2023 48.61 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -220 & HTC-473/2735 completed. Palakkad Proj AE 3
07 Nov 2023 48.38 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -220 & HTC-471/2735 completed. Palakkad Proj AE 3
06 Nov 2023 48.13 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -179 & HTC-449/2735 completed. Palakkad Proj AE 3
04 Nov 2023 48.13 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -179 & HTC-449/2735 completed. Palakkad Proj AE 3
03 Nov 2023 48.00 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -179 & HTC-449/2735 completed. Palakkad Proj AE 3
02 Nov 2023 47.92 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -179 & HTC-449/2735 completed. Palakkad Proj AE 3