Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 May 2024 | 63.2258/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. Base slab concreting finished for valve chamber. 2 LL GLSR Tank site :Curing cover slab and side wall of valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Compound wall 2 side completed. Road restoration works in Palakkayam-Payappullu road in progress(Ward-7).Total connection completed - 887 Nos. (358 FHTC + 529 HTC) Primary Geo Tagg Completed - 855 Nos. (349 FHTC + 506 HTC) | Palakkad Proj AE 3 | |
10 May 2024 | 63.225/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. Base slab concreting finished for valve chamber. 2 LL GLSR Tank site :Curing cover slab and side wall of valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Compound wall 2 side completed.Road restoration works in Palakkayam-Payappullu road in progress(Ward-7).Total connection completed - 884 Nos. (357 FHTC + 527 HTC) Primary Geo Tagg Completed - 854 Nos. (348 FHTC + 506 HTC) | Palakkad Proj AE 3 | |
06 May 2024 | 63.055/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. Base slab concreting finished for valve chamber. 2 LL GLSR Tank site :Curing cover slab and side wall of valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Compound wall 2 side completed.Road restoration works in Palakkayam-Payappullu road in progress(Ward-7).Total connection completed - 869 Nos. (355 FHTC + 514 HTC) Primary Geo Tagg Completed - 850 Nos. (348 FHTC + 502 HTC) | Palakkad Proj AE 3 | |
06 May 2024 | 63.055/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. Base slab concreting finished for valve chamber. 2 LL GLSR Tank site :Curing cover slab and side wall of valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Compound wall 2 side completed.Road restoration works in Palakkayam-Payappullu road in progress(Ward-7).Total connection completed - 869 Nos. (355 FHTC + 514 HTC) Primary Geo Tagg Completed - 850 Nos. (348 FHTC + 502 HTC) | Palakkad Proj AE 3 | |
04 May 2024 | 63.055/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. Base slab concreting finished for valve chamber. 2 LL GLSR Tank site :Curing cover slab and side wall of valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Compound wall 2 side completed.Road restoration works in Palakkayam-Payappullu road in progress(Ward-7).Total connection completed - 869 Nos. (355 FHTC + 514 HTC) Primary Geo Tagg Completed - 850 Nos. (348 FHTC + 502 HTC) | Palakkad Proj AE 3 | |
03 May 2024 | 63.0063/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. Base slab concreting finished for valve chamber. 2 LL GLSR Tank site :Curing cover slab and side wall of valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Compound wall 2 side completed.Road restoration works in Palakkayam-Payappullu road in progress(Ward-7).Total connection completed - 868 Nos. (354 FHTC + 514 HTC) Primary Geo Tagg Completed - 849 Nos. (348 FHTC + 501 HTC) | Palakkad Proj AE 3 | |
02 May 2024 | 63.0063/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. Base slab concreting finished for valve chamber. 2 LL GLSR Tank site :Curing cover slab and side wall of valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Compound wall 2 side completed.Road restoration works in Palakkayam-Payappullu road in progress(Ward-7).Total connection completed - 868 Nos. (354 FHTC + 514 HTC) Primary Geo Tagg Completed - 849 Nos. (348 FHTC + 501 HTC) | Palakkad Proj AE 3 | |
30 Apr 2024 | 63.0063/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. Base slab concreting finished for valve chamber. 2 LL GLSR Tank site :Curing cover slab and side wall of valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Compound wall 2 side completed.Road restoration work in Palakkayam-Payappullu road (Ward-7).Total connection completed - 868 Nos. (354 FHTC + 514 HTC) Primary Geo Tagg Completed - 849 Nos. (348 FHTC + 501 HTC) | Palakkad Proj AE 3 | |
29 Apr 2024 | 62.930/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. Base slab concreting finished for valve chamber. 2 LL GLSR Tank site :Curing cover slab and side wall of valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Compound wall 2 side completed.Road restoration work in palakkayam - payapullu road. PWD road work (Kanjirappuzha - Palakkayam - Injikkunnu PWD road) progressing.Total connection completed - 864 Nos. (352 FHTC + 512 HTC) Primary Geo Tagg Completed - 846 Nos. (348 FHTC + 498 HTC) | Palakkad Proj AE 3 | |
24 Apr 2024 | 62.930/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. Base slab concreting finished for valve chamber. 2 LL GLSR Tank site :Curing cover slab and side wall of valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Compound wall 2 side completed. road restoration work & inter connection work progressing. PWD road work (Kanjirappuzha - Palakkayam - Injikkunnu PWD road) progressing.Total connection completed - 864 Nos. (352 FHTC + 512 HTC) Primary Geo Tagg Completed - 846 Nos. (348 FHTC + 498 HTC) | Palakkad Proj AE 3 |