08 Jun 2024 63.346.0/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Road restoration works on going.Total connection completed -905 Nos. (363 FHTC + 542 HTC) Primary Geo Tagg Completed - 883 Nos. (363 FHTC + 520 HTC) Palakkad Proj AE 3
06 Jun 2024 63.34630/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Road restoration works on going.Total connection completed -900 Nos. (363 FHTC + 537 HTC) Primary Geo Tagg Completed - 881 Nos. (363 FHTC + 518 HTC) Palakkad Proj AE 3
04 Jun 2024 63.280/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber. Cover slab and side wall of valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Compound wall 2 side completed. Road restoration works on going.Total connection completed -900 Nos. (363 FHTC + 537 HTC) Primary Geo Tagg Completed - 881 Nos. (363 FHTC + 518 HTC) Palakkad Proj AE 3
30 May 2024 63.280/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber. Cover slab and side wall of valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Compound wall 2 side completed. Road restoration works on going.Total connection completed -893 Nos. (363 FHTC + 530 HTC) Primary Geo Tagg Completed - 873 Nos. (358 FHTC + 515 HTC) Palakkad Proj AE 3
27 May 2024 63.280/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber.Cover slab and side wall of valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Compound wall 2 side completed. Road restoration works on going.Total connection completed -893 Nos. (363 FHTC + 530 HTC) Primary Geo Tagg Completed - 873 Nos. (358 FHTC + 515 HTC) Palakkad Project Dn EE
25 May 2024 63.280/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber.Cover slab and side wall of valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Compound wall 2 side completed. Road restoration works on going.Total connection completed -893 Nos. (363 FHTC + 530 HTC) Primary Geo Tagg Completed - 873 Nos. (358 FHTC + 515 HTC) Palakkad Project Dn EE
22 May 2024 63.280/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber.Cover slab and side wall of valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Compound wall 2 side completed. Road restoration works on going.Total connection completed -893 Nos. (363 FHTC + 530 HTC) Primary Geo Tagg Completed - 873 Nos. (358 FHTC + 515 HTC) Palakkad Project Dn EE
20 May 2024 63.280/70 km laying completed. Remaining HDPE, DI & GI pipe gap work progressing. 2 LL GLSR Tank site : Base slab concreting finished for valve chamber.Cover slab and side wall of valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Compound wall 2 side completed. Road restoration works on going.Total connection completed -893 Nos. (363 FHTC + 530 HTC) Primary Geo Tagg Completed - 873 Nos. (358 FHTC + 515 HTC) Palakkad Project Dn EE
18 May 2024 63.280/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. Base slab concreting finished for valve chamber. 2 LL GLSR Tank site :Curing cover slab and side wall of valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Compound wall 2 side completed. Road restoration works in Palakkayam - Payappullu road in progress(Ward-7).Total connection completed - 890 Nos. (360 FHTC + 530 HTC) Primary Geo Tagg Completed - 868 Nos. (356 FHTC + 512 HTC). Palakkad Proj AE 3
15 May 2024 63.248/70 km laying completed. Remaining HDPE, DI & GI pipe laying work progressing. Base slab concreting finished for valve chamber. 2 LL GLSR Tank site :Curing cover slab and side wall of valve chamber. Pumping main from GLSR 90% completed & valve fixing work completed. Compound wall 2 side completed. Road restoration works in Palakkayam - Payappullu road in progress(Ward-7).Total connection completed - 889 Nos. (359 FHTC + 530 HTC) Primary Geo Tagg Completed - 860 Nos. (352 FHTC + 508 HTC). Palakkad Proj AE 3