Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Jan 2024 110.68/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, road crossing work completed. Railway permission obtained.2558/8298 no's HTC completed, Ongallur plant road levelling work on going. Palakkad Project Dn AE
18 Jan 2024 110.59/ 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, road crossing work completed. Railway permission obtained.2558/8298 no's HTC completed, Ongallur plant road levelling work on going. Palakkad Project Dn AE
17 Jan 2024 110.59/ 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, Railway permission obtained.2558/8298 no's HTC completed, Ongallur plant road levelling work on going. Palakkad Project Dn AE
16 Jan 2024 110.59/ 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, Railway permission obtained.2558/8298 no's HTC completed, Ongallur plant road levelling work on going. Palakkad Project Dn AE
12 Jan 2024 110.40/ 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, Railway permission obtained.2548/8298 no's HTC completed, Ongallur plant road levelling work on going. Palakkad Project Dn AE
11 Jan 2024 110.01/ 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, Railway permission obtained.2548/8298 no's HTC completed, Ongallur plant road levelling work on going. Palakkad Project Dn AE
10 Jan 2024 110.01/ 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, Railway permission obtained.2548/8298 no's HTC completed, Ongallur plant road levelling work on going. Palakkad Project Dn AE
09 Jan 2024 110.01/ 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, Railway permission obtained.2548/8298 no's HTC completed, Ongallur plant road levelling work on going. Palakkad Project Dn AE
08 Jan 2024 110.01/ 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, Railway permission obtained.2548/8298 no's HTC completed, Ongallur plant road levelling work on going. Palakkad Project Dn AE
06 Jan 2024 109.77/ 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, Railway permission obtained.2548/8298 no's HTC completed. Palakkad Project Dn AE