Status Date |
Overall Project Status |
Project Officer |
Contact |
19 Jan 2024 |
110.68/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, road crossing work completed. Railway permission obtained.2558/8298 no's HTC completed, Ongallur plant road levelling work on going.
|
Palakkad Project Dn AE |
|
18 Jan 2024 |
110.59/ 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, road crossing work completed. Railway permission obtained.2558/8298 no's HTC completed, Ongallur plant road levelling work on going.
|
Palakkad Project Dn AE |
|
17 Jan 2024 |
110.59/ 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, Railway permission obtained.2558/8298 no's HTC completed, Ongallur plant road levelling work on going. |
Palakkad Project Dn AE |
|
16 Jan 2024 |
110.59/ 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, Railway permission obtained.2558/8298 no's HTC completed, Ongallur plant road levelling work on going. |
Palakkad Project Dn AE |
|
12 Jan 2024 |
110.40/ 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, Railway permission obtained.2548/8298 no's HTC completed, Ongallur plant road levelling work on going.
|
Palakkad Project Dn AE |
|
11 Jan 2024 |
110.01/ 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, Railway permission obtained.2548/8298 no's HTC completed, Ongallur plant road levelling work on going.
|
Palakkad Project Dn AE |
|
10 Jan 2024 |
110.01/ 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, Railway permission obtained.2548/8298 no's HTC completed, Ongallur plant road levelling work on going. |
Palakkad Project Dn AE |
|
09 Jan 2024 |
110.01/ 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, Railway permission obtained.2548/8298 no's HTC completed, Ongallur plant road levelling work on going. |
Palakkad Project Dn AE |
|
08 Jan 2024 |
110.01/ 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, Railway permission obtained.2548/8298 no's HTC completed, Ongallur plant road levelling work on going. |
Palakkad Project Dn AE |
|
06 Jan 2024 |
109.77/ 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, Railway permission obtained.2548/8298 no's HTC completed. |
Palakkad Project Dn AE |
|