Status Date |
Overall Project Status |
Project Officer |
Contact |
15 Nov 2023 |
95.88 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2467/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
14 Nov 2023 |
95.88 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2453/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
13 Nov 2023 |
95.88 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2453/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
10 Nov 2023 |
95.51 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2449/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
09 Nov 2023 |
95.51 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2449/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
08 Nov 2023 |
95.51 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2449/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
07 Nov 2023 |
95.29 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2415/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
06 Nov 2023 |
95.29 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2415/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
04 Nov 2023 |
95.02 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2415/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
03 Nov 2023 |
94.82 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2407/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|