Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Mar 2024 Work in progress | 53% Completed | 02/03/2024 117.5/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2824/8298 no's HTC completed, Ongallur plant road levelling work on going Palakkad Project Dn AE
11 Mar 2024 Work in progress | 53% Completed | 02/03/2024 117.5/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2796/8298 no's HTC completed, Ongallur plant road levelling work on going Palakkad Project Dn AE
06 Mar 2024 Work in progress | 53% Completed | 02/03/2024 117.5/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2772/8298 no's HTC completed, Ongallur plant road levelling work on going Palakkad Project Dn AE
02 Mar 2024 Work in progress | 53% Completed | 02/03/2024 117.5/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2714/8298 no's HTC completed, Ongallur plant road levelling work on going Palakkad Project Dn AE
22 Feb 2024 117.5/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2681/8298 no's HTC completed, Ongallur plant road levelling work on going Palakkad Project Dn AEE3
19 Feb 2024 117.5/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2668/8298 no's HTC completed, Ongallur plant road levelling work on going Palakkad Project Dn AEE3
16 Feb 2024 117.5/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2657/8298 no's HTC completed, Ongallur plant road levelling work on going Palakkad Project Dn AE4
15 Feb 2024 117.5/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2647/8298 no's HTC completed, Ongallur plant road levelling work on going Palakkad Project Dn AE
14 Feb 2024 117.5/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2639/8298 no's HTC completed, Ongallur plant road levelling work on going Palakkad Project Dn AE
13 Feb 2024 117.5/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2631/8298 no's HTC completed, Ongallur plant road levelling work on going Palakkad Project Dn AE