Status Date |
Overall Project Status |
Project Officer |
Contact |
28 Nov 2023 |
98.53 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2527/8298 no's HTC completed
|
Palakkad Project Dn AE |
|
27 Nov 2023 |
98.04 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2527/8298 no's HTC completed
|
Palakkad Project Dn AE |
|
25 Nov 2023 |
97.75 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2513/8298 no's HTC completed |
Palakkad Project Dn AE |
|
24 Nov 2023 |
97.55 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2482/8298 no's HTC completed
|
Palakkad Project Dn AE |
|
23 Nov 2023 |
97.55 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2482/8298 no's HTC completed
|
Palakkad Project Dn AE |
|
22 Nov 2023 |
96.82 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2482/8298 no's HTC completed |
Palakkad Project Dn AE |
|
21 Nov 2023 |
96.37 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2482/8298 no's HTC completed |
Palakkad Project Dn AE |
|
20 Nov 2023 |
96.37 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2482/8298 no's HTC completed |
Palakkad Project Dn AE |
|
18 Nov 2023 |
96.37 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2477/8298 no's HTC completed. |
Palakkad Project Dn AE |
|
17 Nov 2023 |
96.37 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2477/8298 no's HTC completed. |
Palakkad Project Dn AE |
|