Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Apr 2024 Work in progress 118.314/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2882/8298 no's HTC completed & 2741 nos Geo tagged & 0 FHTC's, Ongallur plant road levelling work on going Palakkad Project Dn AEE3
30 Mar 2024 Work in progress 118.086/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2874/8298 no's HTC completed & 2732 nos Geo tagged & 0 FHTC's, Ongallur plant road levelling work on going Palakkad Project Dn AEE3
27 Feb 2024 Work in progress 118.086/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2867/8298 no's HTC completed & 2732 nos Geo tagged & 0 FHTC's, Ongallur plant road levelling work on going Palakkad Project Dn AEE3
26 Mar 2024 Work in progress 118.086/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2862/8298 no's HTC completed & 2728 nos Geo tagged & 0 FHTC's, Ongallur plant road levelling work on going Palakkad Project Dn AEE3
27 Mar 2024 Work in progress 1/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2862/8298 no's HTC completed & 2728 nos Geo tagged & 0 FHTC's, Ongallur plant road levelling work on going Palakkad Project Dn AEE3
26 Mar 2024 Work in progress 1/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2858/8298 no's HTC completed & 2723 nos Geo tagged & 0 FHTC's, Ongallur plant road levelling work on going Palakkad Project Dn AEE3
25 Mar 2024 Work in progress 117.894/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2858/8298 no's HTC completed & 2723 nos Geo tagged & 0 FHTC's, Ongallur plant road levelling work on going Palakkad Project Dn AEE3
22 Mar 2024 Work in progress 117.725/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2848/8298 no's HTC completed & 2723 nos Geo tagged, Ongallur plant road levelling work on going Palakkad Project Dn AE 4
21 Mar 2024 Work in progress 117.568/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2838/8298 no's HTC completed & 2716 nos Geo tagged, Ongallur plant road levelling work on going Palakkad Project Dn AE 4
20 Mar 2024 Work in progress 117.568/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2835/8298 no's HTC completed & 2716 nos Geo tagged, Ongallur plant road levelling work on going Palakkad Project Dn AE 4