Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Jun 2024 Work in progress 120.052/ 174.70 km laying completed. Remaining pipe laying work progressing.3183/8298 House connections completed & 3064 nos Geo tagged & 0 FHTC's Palakkad Project Dn AEE3
26 Jun 2024 Work in progress 120.052/ 174.70 km laying completed. Remaining pipe laying work progressing.3183/8298 House connections completed & 3064 nos Geo tagged & 0 FHTC's Palakkad Project Dn AEE3
25 Jun 2024 Work in progress 120.052/ 174.70 km laying completed. Remaining pipe laying work progressing.3183/8298 House connections completed & 3059 nos Geo tagged & 0 FHTC's Palakkad Project Dn AEE3
22 Jun 2024 Work in progress 119.968/ 174.70 km laying completed. Remaining pipe laying work progressing.3178/8298 House connections completed & 3029 nos Geo tagged & 0 FHTC's Palakkad Project Dn AEE3
20 Jun 2024 Work in progress 119.91519/ 174.70 km laying completed. Remaining pipe laying work progressing.3171/8298 House connections completed & 3021 nos Geo tagged & 0 FHTC's. Palakkad Project Dn AEE3
15 Jun 2024 Work in progress 119.812/ 174.70 km laying completed. Remaining pipe laying work progressing.3148/8298 House connections completed & 2997 nos Geo tagged & 0 FHTC's. Palakkad Project Dn AEE3
13 Jun 2024 Work in progress 119.662/ 174.70 km laying completed. Remaining pipe laying work progressing.3143/8298 House connections completed & 2987 nos Geo tagged & 0 FHTC's. Palakkad Project Dn AEE3
11 Jun 2024 Work in progress 119.636/ 174.70 km laying completed. Remaining pipe laying work progressing.3130/8298 House connections completed & 2980 nos Geo tagged & 0 FHTC's. Palakkad Project Dn AEE3
08 Jun 2024 Work in progress 119.636/ 174.70 km laying completed. Remaining pipe laying work progressing.3117/8298 House connections completed & 2954 nos Geo tagged & 0 FHTC's. Palakkad Project Dn AEE3
06 Jun 2024 Work in progress 119.636/ 174.70 km laying completed. Remaining pipe laying work progressing.3101/8298 House connections completed & 2954 nos Geo tagged & 0 FHTC's. Palakkad Project Dn AEE3