Status Date |
Overall Project Status |
Project Officer |
Contact |
11 Dec 2023 |
102.61 / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2533/8298 no's HTC completed, road levelling work ( PHC & KWA plant) on going.
|
Palakkad Project Dn AE |
|
08 Dec 2023 |
101.48 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2533/8298 no's HTC completed
|
Palakkad Project Dn AE |
|
07 Dec 2023 |
101.15 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2533/8298 no's HTC completed
|
Palakkad Project Dn AE |
|
06 Dec 2023 |
99.33 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2533/8298 no's HTC completed
|
Palakkad Project Dn AE |
|
05 Dec 2023 |
99.33 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2533/8298 no's HTC completed
|
Palakkad Project Dn AE |
|
04 Dec 2023 |
99.33 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2533/8298 no's HTC completed |
Palakkad Project Dn AE |
|
02 Dec 2023 |
99.33 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2533/8298 no's HTC completed
|
Palakkad Project Dn AE |
|
01 Dec 2023 |
99.33 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2533/8298 no's HTC completed
|
Palakkad Project Dn AE |
|
30 Nov 2023 |
98.63 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2527/8298 no's HTC completed
|
Palakkad Project Dn AE |
|
29 Nov 2023 |
98.63 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2527/8298 no's HTC completed
|
Palakkad Project Dn AE |
|