Status Date |
Overall Project Status |
Project Officer |
Contact |
07 Feb 2024 |
117.5/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2558/8298 no's HTC completed, Ongallur plant road levelling work on going. |
Palakkad Project Dn AE |
|
31 Jan 2024 |
111.71/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, road crossing work completed. Railway permission obtained.2558/8298 no's HTC completed, Ongallur plant road levelling work on going. |
Palakkad Project Dn AE |
|
30 Jan 2024 |
111.71/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, road crossing work completed. Railway permission obtained.2558/8298 no's HTC completed, Ongallur plant road levelling work on going. |
Palakkad Project Dn AE |
|
29 Jan 2024 |
111.71/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, road crossing work completed. Railway permission obtained.2558/8298 no's HTC completed, Ongallur plant road levelling work on going.
|
Palakkad Project Dn AE |
|
27 Jan 2024 |
111.53/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, road crossing work completed. Railway permission obtained.2558/8298 no's HTC completed, Ongallur plant road levelling work on going.
|
Palakkad Project Dn AE |
|
25 Jan 2024 |
111.53/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, road crossing work completed. Railway permission obtained.2558/8298 no's HTC completed, Ongallur plant road levelling work on going.
|
Palakkad Project Dn AE |
|
24 Jan 2024 |
111.53/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, road crossing work completed. Railway permission obtained.2558/8298 no's HTC completed, Ongallur plant road levelling work on going.
|
Palakkad Project Dn AE |
|
23 Jan 2024 |
110.89/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, road crossing work completed. Railway permission obtained.2558/8298 no's HTC completed, Ongallur plant road levelling work on going.
|
Palakkad Project Dn AE |
|
22 Jan 2024 |
110.89/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, road crossing work completed. Railway permission obtained.2558/8298 no's HTC completed, Ongallur plant road levelling work on going.
|
Palakkad Project Dn AE |
|
20 Jan 2024 |
110.89/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going, road crossing work completed. Railway permission obtained.2558/8298 no's HTC completed, Ongallur plant road levelling work on going.
|
Palakkad Project Dn AE |
|