Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Apr 2024 Work in progress 119.105/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2950/8298 no's HTC completed & 2839 nos Geo tagged & 0 FHTC's, Ongallur plant road levelling work on going. Palakkad Project Dn AEE3
17 Apr 2024 Work in progress 119.079/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2943/8298 no's HTC completed & 2832 nos Geo tagged & 0 FHTC's, Ongallur plant road levelling work on going. Palakkad Project Dn AEE3
16 Apr 2024 Work in progress 119.040/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2943/8298 no's HTC completed & 2826 nos Geo tagged & 0 FHTC's, Ongallur plant road levelling work on going. Palakkad Project Dn AEE3
15 Apr 2024 Work in progress 118.979/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2943/8298 no's HTC completed & 2826 nos Geo tagged & 0 FHTC's, Ongallur plant road levelling work on going. Palakkad Project Dn AEE3
12 Apr 2024 Work in progress 118.886/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2932/8298 no's HTC completed & 2808 nos Geo tagged & 0 FHTC's, Ongallur plant road levelling work on going Palakkad Project Dn AEE3
09 Apr 2024 Work in progress 118.603/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2921/8298 no's HTC completed & 2796 nos Geo tagged & 0 FHTC's, Ongallur plant road levelling work on going Palakkad Project Dn AEE3
08 Apr 2024 Work in progress 118.565/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2919/8298 no's HTC completed & 2790 nos Geo tagged & 0 FHTC's, Ongallur plant road levelling work on going Palakkad Project Dn AEE3
06 Apr 2024 Work in progress 118.550/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2919/8298 no's HTC completed & 2777 nos Geo tagged & 0 FHTC's, Ongallur plant road levelling work on going Palakkad Project Dn AEE3
03 Apr 2024 Work in progress 118.352/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2899/8298 no's HTC completed & 2758 nos Geo tagged & 0 FHTC's, Ongallur plant road levelling work on going Palakkad Project Dn AEE3
02 Apr 2024 Work in progress 118.352/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). Railway permission obtained.2892/8298 no's HTC completed & 2750 nos Geo tagged & 0 FHTC's, Ongallur plant road levelling work on going Palakkad Project Dn AEE3