Status Date |
Overall Project Status |
Project Officer |
Contact |
19 Oct 2023 |
93.21 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2369/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
18 Oct 2023 |
93.21 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2369/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
17 Oct 2023 |
93.21 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2369/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
16 Oct 2023 |
92.49 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2369/8298 no's HTC completed. |
Palakkad Project Dn AE |
|
13 Oct 2023 |
92.04 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2369/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
12 Oct 2023 |
91.80 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained, .2365/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
11 Oct 2023 |
91.63 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained, .2363/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
10 Oct 2023 |
91.36 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained, .2363/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
09 Oct 2023 |
91.36 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained, .2363/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
07 Oct 2023 |
90.49 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained, .2363/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|