Overall Project Status

Status Date Overall Project Status Project Officer Contact
06 Oct 2023 90.49 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained, .2363/8298 no's HTC completed. Palakkad Project Dn AE
05 Oct 2023 89.45 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained, .2363/8298 no's HTC completed. Palakkad Project Dn AE
04 Oct 2023 88.89 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2363/8298 no's HTC completed. Palakkad Project Dn AE
03 Oct 2023 88.89 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2363/8298 no's HTC completed. Palakkad Project Dn AE
30 Sep 2023 88.89 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2363/8298 no's HTC completed. Palakkad Project Dn AE
29 Sep 2023 88.40 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2311 no's HTC completed. Palakkad Project Dn AE
27 Sep 2023 88.40 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2311 no's HTC completed. Palakkad Project Dn AE
26 Sep 2023 87.47 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2311 no's HTC completed. Palakkad Project Dn AE
25 Sep 2023 86.63 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2311 no's HTC completed. Palakkad Project Dn AE
23 Sep 2023 86.63 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2311 no's HTC completed. Palakkad Project Dn AE