Status Date |
Overall Project Status |
Project Officer |
Contact |
02 Nov 2023 |
94.55 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2407/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
01 Nov 2023 |
94.55 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2407/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
31 Oct 2023 |
94.55 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2407/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
30 Oct 2023 |
94.30 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2407/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
28 Oct 2023 |
94.05 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2407/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
27 Oct 2023 |
94.05 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2407/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
26 Oct 2023 |
94.05 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2392/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
25 Oct 2023 |
93.66 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2392/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
21 Oct 2023 |
93.66 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2392/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|
20 Oct 2023 |
93.66 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, ongallur- karakkad road work on going, Railway permission obtained.2392/8298 no's HTC completed.
|
Palakkad Project Dn AE |
|