Status Date |
Overall Project Status |
Project Officer |
Contact |
21 Sep 2023 |
85.98 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2311 no's HTC completed. |
Palakkad Project Dn AE |
|
20 Sep 2023 |
85.67 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2292 no's HTC completed. |
Palakkad Project Dn AE |
|
19 Sep 2023 |
85.67 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2292 no's HTC completed. |
Palakkad Project Dn AE |
|
18 Sep 2023 |
85.67 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2292 no's HTC completed. |
Palakkad Project Dn AE |
|
16 Sep 2023 |
85.67 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2274 no's HTC completed. |
Palakkad Project Dn AE |
|
14 Sep 2023 |
83.25 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2274 no's HTC completed. |
Palakkad Project Dn AE |
|
13 Sep 2023 |
82.81 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2261 no's HTC completed. |
Palakkad Project Dn AE |
|
12 Sep 2023 |
82.38 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) started, Railway permission obtained, .2246 no's HTC completed. |
Palakkad Project Dn AE |
|
11 Sep 2023 |
82.34 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) started, Railway permission obtained, .2246 no's HTC completed. |
Palakkad Project Dn AE |
|
08 Sep 2023 |
82.16 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) started, Railway permission obtained, .2238 no's HTC completed. |
Palakkad Project Dn AE |
|