Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Sep 2023 85.98 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2311 no's HTC completed. Palakkad Project Dn AE
20 Sep 2023 85.67 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2292 no's HTC completed. Palakkad Project Dn AE
19 Sep 2023 85.67 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2292 no's HTC completed. Palakkad Project Dn AE
18 Sep 2023 85.67 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2292 no's HTC completed. Palakkad Project Dn AE
16 Sep 2023 85.67 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2274 no's HTC completed. Palakkad Project Dn AE
14 Sep 2023 83.25 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2274 no's HTC completed. Palakkad Project Dn AE
13 Sep 2023 82.81 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) on going, Railway permission obtained, .2261 no's HTC completed. Palakkad Project Dn AE
12 Sep 2023 82.38 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) started, Railway permission obtained, .2246 no's HTC completed. Palakkad Project Dn AE
11 Sep 2023 82.34 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) started, Railway permission obtained, .2246 no's HTC completed. Palakkad Project Dn AE
08 Sep 2023 82.16 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) started, Railway permission obtained, .2238 no's HTC completed. Palakkad Project Dn AE