Status Date |
Overall Project Status |
Project Officer |
Contact |
07 Sep 2023 |
82.16 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) started, Railway permission obtained, .2238 no's HTC completed. |
Palakkad Project Dn AE |
|
05 Sep 2023 |
82.16 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, PWD road crossing completed, ( ongallur- karakkad road ) started, Railway permission obtained, .2238 no's HTC completed. |
Palakkad Project Dn AE |
|
04 Sep 2023 |
81.59 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed , PWD road crossing completed, ( ongallur- karakkad road ) started, Railway permission ( crossing between vadanakkurissi -shoranur) not issued, .2186 no's HTC completed. |
Palakkad Project Dn AE |
|
02 Sep 2023 |
81.59 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed , PWD road crossing completed, ( ongallur- karakkad road ) started, Railway permission ( crossing between vadanakkurissi -shoranur) not issued, .2186 no's HTC completed. |
Palakkad Project Dn AE |
|
01 Sep 2023 |
81.59 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed , PWD road crossing completed, ( ongallur- karakkad road ) started, Railway permission ( crossing between vadanakkurissi -shoranur) not issued, .2186 no's HTC completed. |
Palakkad Project Dn AE |
|
26 Aug 2023 |
81.59 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed , PWD road crossing completed, ( ongallur- karakkad road ) started, Railway permission ( crossing between vadanakkurissi -shoranur) not issued, .2186 no's HTC completed. |
Palakkad Project Dn AE |
|
25 Aug 2023 |
81.59 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed , PWD road crossing completed, ( ongallur- karakkad road ) started, Railway permission ( crossing between vadanakkurissi -shoranur) not issued, .2186 no's HTC completed. |
Palakkad Project Dn AE |
|
24 Aug 2023 |
80.96 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed , PWD road crossing completed, restoration work progressing. Railway permission ( crossing between vadanakkurissi -shoranur, crossing between pattambi - karakkad) not issued.2176 no's HTC completed. |
Palakkad Project Dn AE |
|
23 Aug 2023 |
80.71 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed , PWD road crossing completed, restoration work progressing. Railway permission ( crossing between vadanakkurissi -shoranur, crossing between pattambi - karakkad) not issued.2154 no's HTC completed. |
Palakkad Project Dn AE |
|
22 Aug 2023 |
80.71 km / 174.70 km completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed , PWD road crossing completed, restoration work progressing. Railway permission ( crossing between vadanakkurissi -shoranur, crossing between pattambi - karakkad) not issued.2154 no's HTC completed. |
Palakkad Project Dn AE |
|