Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Mar 2023 Pack-1 Work of OHSR has been completed 100%-on 17.03.2022 Pack-2-balance work- Work has been completed | 100% Completed | 31/03/2023 work completed on 28.01.2023 Chittur Project Dn - AE 3
24 Mar 2023 Work in progress | 98% Completed | 24/03/2023 pack-2-KIIFb-leak rectification work in progress,painting work completed,linking works are also balance Chittur Project Dn - AE 3
05 Mar 2023 Work in progress | 98% Completed | 05/03/2023 pack-2-KIIFb-leak rectification work in progress,painting work completed,linking works are also balance Chittur Project Dn - AE 3
24 Feb 2023 Work in progress | 98% Completed | 24/02/2023 pack-2-KIIFb-leak rectification work in progress,painting work completed,linking works are also balance Chittur Project Dn - AE 3
17 Feb 2023 Work in progress | 98% Completed | 17/02/2023 pack-2-KIIFb-leak rectification work in progress,painting work completed,linking works are also balance Chittur Project Dn - AE 3
10 Feb 2023 Work in progress | 98% Completed | 10/02/2023 pack-2-KIIFb-leak rectification work in progress,painting work completed,linking works are also balance Chittur Project Dn - AE 3
03 Feb 2023 Work in progress | 98% Completed | 03/02/2023 pack-2-KIIFb-leak rectification work in progress,painting work completed,Manhole cover and identification stone work name board works are also balance Chittur Project Dn - AE 3
20 Jan 2023 Work in progress | 98% Completed | 20/01/2023 pack-2-KIIFb-leak rectification work in progress,painting work completed,Manhole cover and identification stone work name board works are also balance Chittur Project Dn - AE 3
06 Jan 2023 Work in progress | 98% Completed | 06/01/2023 pack-2-leak rectification work in progress,painting work completed,Manhole cover and identification stone work name board works are also balance Chittur Project Dn - AE 3
22 Dec 2022 Work in progress | 98% Completed | 22/12/2022 pack-2-KIIFB Officer site Inspecting ,leak rectification work in progress,painting work completed,Manhole cover and identification stone work name board works are also balance Chittur Project Dn - AE 3