Status Date |
Overall Project Status |
Project Officer |
Contact |
31 Mar 2023 |
Pack-1
Work of OHSR has been completed 100%-on 17.03.2022
Pack-2-balance work-
Work has been completed | 100% Completed | 31/03/2023
work completed on 28.01.2023
|
Chittur Project Dn - AE 3 |
|
24 Mar 2023 |
Work in progress | 98% Completed | 24/03/2023 pack-2-KIIFb-leak rectification work in progress,painting work completed,linking works are also balance |
Chittur Project Dn - AE 3 |
|
05 Mar 2023 |
Work in progress | 98% Completed | 05/03/2023
pack-2-KIIFb-leak rectification work in progress,painting work completed,linking works are also balance |
Chittur Project Dn - AE 3 |
|
24 Feb 2023 |
Work in progress | 98% Completed | 24/02/2023
pack-2-KIIFb-leak rectification work in progress,painting work completed,linking works are also balance |
Chittur Project Dn - AE 3 |
|
17 Feb 2023 |
Work in progress | 98% Completed | 17/02/2023
pack-2-KIIFb-leak rectification work in progress,painting work completed,linking works are also balance |
Chittur Project Dn - AE 3 |
|
10 Feb 2023 |
Work in progress | 98% Completed | 10/02/2023
pack-2-KIIFb-leak rectification work in progress,painting work completed,linking works are also balance |
Chittur Project Dn - AE 3 |
|
03 Feb 2023 |
Work in progress | 98% Completed | 03/02/2023
pack-2-KIIFb-leak rectification work in progress,painting work completed,Manhole cover and identification stone work name board works are also balance |
Chittur Project Dn - AE 3 |
|
20 Jan 2023 |
Work in progress | 98% Completed | 20/01/2023
pack-2-KIIFb-leak rectification work in progress,painting work completed,Manhole cover and identification stone work name board works are also balance |
Chittur Project Dn - AE 3 |
|
06 Jan 2023 |
Work in progress | 98% Completed | 06/01/2023
pack-2-leak rectification work in progress,painting work completed,Manhole cover and identification stone work name board works are also balance |
Chittur Project Dn - AE 3 |
|
22 Dec 2022 |
Work in progress | 98% Completed | 22/12/2022
pack-2-KIIFB Officer site Inspecting ,leak rectification work in progress,painting work completed,Manhole cover and identification stone work name board works are also balance |
Chittur Project Dn - AE 3 |
|