Status Date |
Overall Project Status |
Project Officer |
Contact |
30 Jul 2021 |
Phase-II-pack-II
Work in progress | 76% Completed | 30/07/2021
Kadampidi ohsr 250mm column pipe fixing ,and painting work also in progress.
PACK-1
Work in progress | 95% Completed | 30/07/2021
95% of work complete except Finishing work
|
Chittur Project Dn - AE 3 |
|
28 Jul 2021 |
Pack-2
Work in progress | 76% Completed | 28/07/2021
.Kadampidi ohsr 250mm column pipe fixing , work in progress.
Pack-1
Work in progress | 95% Completed | 28/07/2021
95% of work complete except Finishing work
|
Chittur Project Dn - AE 3 |
|
24 Jul 2021 |
Pack-2
Work in progress | 76% Completed | 24/07/2021
9.50 LL OHSR-Painting work finishing stage in progress.
Pack-1
Work in progress | 95% Completed | 24/07/2021
95% of work complete except Finishing work
|
Chittur Project Dn - AE 3 |
|
19 Jul 2021 |
Pack-2
Work in progress | 75% Completed | 19/07/2021
9.50 LL OHSR-Painting work finishing stage in progress.
Pack-1-part-1
Work in progress | 95% Completed | 19/07/2021
Filling of basement work completed
|
Chittur Project Dn - AE 3 |
|
19 Jul 2021 |
9.5 LL OHSR At kadambidy painting in progress |
Chittur Project Dn - AE 3 |
|
11 Jul 2021 |
Pack-2
Work in progress | 68% Completed | 11/07/2021
9.50 LL OHSR-Painting work in progress.
Pack-1-part-1
Work in progress | 95% Completed | 11/07/2021
Filling of basement work in progress
|
Chittur Project Dn - AE 3 |
|
05 Jul 2021 |
Pack-II Work in progress | 66% Completed | 05/07/2021 White washing first coat work- of 9.50 LL OHSR at Kadambidi Bharathmala in Melarcode Panchayath Pack-1 Work in progress | 95% Completed | 05/07/2021 Structural works,plastering works and Painting works of OHSR completed.Retaining wall,compound wall also completed. Filling of basement work in progress |
Chittur Project Dn - AE 3 |
|
04 Jul 2021 |
Pack-II
Work in progress | 66% Completed | 04/07/2021
White washing first coat work- of 9.50 LL OHSR at Kadambidi Bharathmala in Melarcode Panchayath
Pack-1
Work in progress | 95% Completed | 04/07/2021
Structural works,plastering works and Painting works of OHSR completed.Retaining wall,compound wall also completed. Filling of basement work in progress
|
Chittur Project Dn - AE 3 |
|
28 Jun 2021 |
Pack-1
Work in progress | 95% Completed | 28/06/2021
Structural works,plastering works and Painting works of OHSR completed.Retaining wall,compound wall also completed. Filling of basement work in progress
Pack-2
Work in progress | 65% Completed | 28/06/2021
9.50 LL OHSR white washing first coat work in progress
|
Chittur Project Dn - AE 3 |
|
20 Jun 2021 |
Pack-1
Work in progress | 95% Completed | 20/06/2021
Structural works,plastering works and Painting works of OHSR completed.Retaining wall,compound wall also completed. Filling of basement work in progress
Pack-2
Work in progress | 65% Completed | 20/06/2021
OH TANK-all-around plinth-basement filling work in progress
|
Chittur Project Dn - AE 3 |
|