Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 Jul 2021 Phase-II-pack-II Work in progress | 76% Completed | 30/07/2021 Kadampidi ohsr 250mm column pipe fixing ,and painting work also in progress. PACK-1 Work in progress | 95% Completed | 30/07/2021 95% of work complete except Finishing work Chittur Project Dn - AE 3
28 Jul 2021 Pack-2 Work in progress | 76% Completed | 28/07/2021 .Kadampidi ohsr 250mm column pipe fixing , work in progress. Pack-1 Work in progress | 95% Completed | 28/07/2021 95% of work complete except Finishing work Chittur Project Dn - AE 3
24 Jul 2021 Pack-2 Work in progress | 76% Completed | 24/07/2021 9.50 LL OHSR-Painting work finishing stage in progress. Pack-1 Work in progress | 95% Completed | 24/07/2021 95% of work complete except Finishing work Chittur Project Dn - AE 3
19 Jul 2021 Pack-2 Work in progress | 75% Completed | 19/07/2021 9.50 LL OHSR-Painting work finishing stage in progress. Pack-1-part-1 Work in progress | 95% Completed | 19/07/2021 Filling of basement work completed Chittur Project Dn - AE 3
19 Jul 2021 9.5 LL OHSR At kadambidy painting in progress Chittur Project Dn - AE 3
11 Jul 2021 Pack-2 Work in progress | 68% Completed | 11/07/2021 9.50 LL OHSR-Painting work in progress. Pack-1-part-1 Work in progress | 95% Completed | 11/07/2021 Filling of basement work in progress Chittur Project Dn - AE 3
05 Jul 2021 Pack-II Work in progress | 66% Completed | 05/07/2021 White washing first coat work- of 9.50 LL OHSR at Kadambidi Bharathmala in Melarcode Panchayath Pack-1 Work in progress | 95% Completed | 05/07/2021 Structural works,plastering works and Painting works of OHSR completed.Retaining wall,compound wall also completed. Filling of basement work in progress Chittur Project Dn - AE 3
04 Jul 2021 Pack-II Work in progress | 66% Completed | 04/07/2021 White washing first coat work- of 9.50 LL OHSR at Kadambidi Bharathmala in Melarcode Panchayath Pack-1 Work in progress | 95% Completed | 04/07/2021 Structural works,plastering works and Painting works of OHSR completed.Retaining wall,compound wall also completed. Filling of basement work in progress Chittur Project Dn - AE 3
28 Jun 2021 Pack-1 Work in progress | 95% Completed | 28/06/2021 Structural works,plastering works and Painting works of OHSR completed.Retaining wall,compound wall also completed. Filling of basement work in progress Pack-2 Work in progress | 65% Completed | 28/06/2021 9.50 LL OHSR white washing first coat work in progress Chittur Project Dn - AE 3
20 Jun 2021 Pack-1 Work in progress | 95% Completed | 20/06/2021 Structural works,plastering works and Painting works of OHSR completed.Retaining wall,compound wall also completed. Filling of basement work in progress Pack-2 Work in progress | 65% Completed | 20/06/2021 OH TANK-all-around plinth-basement filling work in progress Chittur Project Dn - AE 3