Status Date |
Overall Project Status |
Project Officer |
Contact |
01 Feb 2022 |
Pack-1
Work in progress | 95% Completed | 01/02/2022
95% of work complete except Finishing work,
Pack-2-balance work
Work in progress | 85% Completed | 01/02/2022
Compound wall brick work &plastering work in progess
|
Chittur Project Dn - AE 3 |
|
26 Jan 2022 |
Pack-1
Work in progress | 95% Completed | 26/01/2022
95% of work complete except Finishing work,
Pack-2
Work in progress | 84% Completed | 26/01/2022
Work in progress | 95% Completed | 26/01/2022 95% of work complete except Finishing work
|
Chittur Project Dn - AE 3 |
|
20 Jan 2022 |
Pack-1
Work in progress | 95% Completed | 20/01/2022
95% of work complete except Finishing work,
Pack-2
Work in progress | 84% Completed | 20/01/2022
compound wall-belt shuttering work in progress
|
Chittur Project Dn - AE 3 |
|
12 Jan 2022 |
Pack-II
Work in progress | 83% Completed | 12/01/2022
Kadambidi 9.5LL OHSR approach road earth work and compound wall work in progress
PACK-I
Work in progress | 95% Completed | 12/01/2022
95% of work complete except Finishing work,
|
Chittur Project Dn - AE 3 |
|
10 Jan 2022 |
Pack-1
Work in progress | 95% Completed | 10/01/2022
95% of work complete except Finishing work,
Pack-2
Work in progress | 83% Completed | 10/01/2022
Kadambidi 9.5LL OHSR approach road earth work and compound wall work in progress
|
Chittur Project Dn - AE 3 |
|
02 Jan 2022 |
pack-1
Work in progress | 95% Completed | 02/01/2022
95% of work complete except Finishing work,
Pack-2
Work in progress | 83% Completed | 02/01/2022
compound wall belt work in progress
|
Chittur Project Dn - AE 3 |
|
28 Dec 2021 |
Pack-2
Work in progress | 83% Completed | 28/12/2021
compound wall belt work in progress
pack-1
Work in progress | 95% Completed | 28/12/2021
95% of work complete except Finishing work,
|
Chittur Project Dn - AE 3 |
|
22 Dec 2021 |
Pack-2
Work in progress | 83% Completed | 22/12/2021
compound wall belt work in progress
pack-1
Work in progress | 95% Completed | 22/12/2021
95% of work complete except Finishing work,
|
Chittur Project Dn - AE 3 |
|
21 Dec 2021 |
Pack-II
Work in progress | 83% Completed | 21/12/2021
compound wall belt work in progress
PACK-1
Work in progress | 95% Completed | 21/12/2021
95% of work complete except Finishing work,
|
Chittur Project Dn - AE 3 |
|
19 Dec 2021 |
PACK-2
Work in progress | 83% Completed | 19/12/2021
basement filling work in progress 1).Pumping main and distribution linking works are almost complete 2).Compound wall -belt work in progress
PACK-1
Work in progress | 95% Completed | 19/12/2021
95% of work complete except Finishing work,
|
Chittur Project Dn - AE 3 |
|