Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
31 Jul 2022 | Work in progress | 96% Completed | 31/07/2022 pack-1- completed,pack-2-filling in Trenches up to Plinth beam of 9.5LL OHSR at Kadambidi and painting work one coat to be done | Chittur Project Dn - AE 3 | |
24 Jul 2022 | pack-1-completed ,pack-2-Earth filling in Trenches upto Plinth beam of 9.5LL OHSR at Kadambidi and painting work one coat to be done | Chittur Project Dn - AE 3 | |
19 Jul 2022 | pack-1-completed ,pack-2-Earth filling in Trenches upto Plinth beam of 9.5LL OHSR at Kadambidi and painting work one coat to be done | Chittur Project Dn - AE 3 | |
15 Jul 2022 | pack-1-completed ,pack-2-Earth filling in Trenches upto Plinth beam of 9.5LL OHSR at Kadambidi and painting work one coat to be done | Chittur Project Dn - AE 3 | |
10 Jul 2022 | pack-1-completed ,pack-2-Earth filling in Trenches upto Plinth beam of 9.5LL OHSR at Kadambidi and painting work one coat to be done | Chittur Project Dn - AE 3 | |
09 Jul 2022 | pack-1-completed ,pack-2-Earth filling in Trenches upto Plinth beam of 9.5LL OHSR at Kadambidi and painting work one coat to be done | Chittur Project Dn - AE 3 | |
06 Jul 2022 | pack-1-completed ,pack-2-Earth filling in Trenches upto Plinth beam of 9.5LL OHSR at Kadambidi | Chittur Project Dn - AE 3 | |
05 Jul 2022 | Earth filling in Trenches upto Plinth beam of 9.5LL OHSR at Kadambidi | Chittur Project Dn - AE 3 | |
20 Jun 2022 | Pack-1-completed Pack-2 Work in progress | 95% Completed |31/05/2022 painting work is to be done | Chittur Project Dn - AE 3 | |
17 Jun 2022 | Pack-1-completed Pack-2 Work in progress | 95% Completed |31/05/2022 painting work is to be done | Chittur Project Dn - AE 3 |