Status Date |
Overall Project Status |
Project Officer |
Contact |
03 Oct 2021 |
Pack-II
Work in progress | 76% Completed | 03/10/2021
1. Pumping main and distribution linking works 2. Compound wall work is to be done 3. Column pipe work in progress
PACK-1
Work in progress | 95% Completed | 03/10/2021
95% of work complete except Finishing work
|
Chittur Project Dn - AE 3 |
|
27 Sep 2021 |
Pack-1
Work in progress | 95% Completed | 27/09/2021
95% of work complete except Finishing work
Pack-2
Work in progress | 76% Completed | 27/09/2021
pumping main and distribution linking works ,compound wall work are to be done
|
Chittur Project Dn - AE 3 |
|
24 Sep 2021 |
Pack-II
Work in progress | 76% Completed | 24/09/2021
pumping main and distribution linking works ,compound wall work are to be done
PACK-I
Work in progress | 95% Completed | 24/09/2021
95% of work complete except Finishing work
|
Chittur Project Dn - AE 3 |
|
21 Sep 2021 |
Pack-II
Work in progress | 76% Completed | 21/09/2021
pumping main and distribution linking works ,compound wall work are to be done
PACK-I-Part-I
Work in progress | 95% Completed | 21/09/2021
95% of work complete except Finishing work
|
Chittur Project Dn - AE 3 |
|
12 Sep 2021 |
Phase-II-PACK-1
Work in progress | 95% Completed | 12/09/2021
95% of work complete except Finishing worK
Phase-II-Pack-2
Work in progress | 76% Completed | 12/09/2021
pumping main and distribution linking works ,compound wall work are to be done
|
Chittur Project Dn - AE 3 |
|
05 Sep 2021 |
Phase-2-pack-1
Work in progress | 95% Completed | 05/09/2021
95% of work complete except Finishing work
Phase-2-pack-2
Work in progress | 76% Completed | 05/09/2021
valve chamber concrete work complete at Kadampidi OHSR in Melarcode
|
Chittur Project Dn - AE 3 |
|
29 Aug 2021 |
Phase-II-
Pack-1
Work in progress | 95% Completed | 29/08/2021
95% of work complete except Finishing work
Pack-II
Work in progress | 76% Completed | 29/08/2021
valve chamber reinforcement work in progress at Kadampidi OHSR in Melarcode
|
Chittur Project Dn - AE 3 |
|
17 Aug 2021 |
PHASE-II-Pack-I
Work in progress | 95% Completed | 17/08/2021
95% of work complete except Finishing work
Phase-II-Pack-II
Work in progress | 76% Completed | 17/08/2021
Scour pipe fixing and valve chamber PCC work in progress
|
Chittur Project Dn - AE 3 |
|
09 Aug 2021 |
Phse-II-Pack-1
Work in progress | 95% Completed | 09/08/2021
95% of work complete except Finishing work
Phase-II-pack-II
Work in progress | 76% Completed | 09/08/2021
350mm DI K9 column pipe fixing work is in progress.
|
Chittur Project Dn - AE 3 |
|
01 Aug 2021 |
pack-2
Work in progress | 76% Completed | 01/08/2021
Kadampidi ohsr 250mm column pipe fixing ,and painting work also in progress.
Pack-1
Work in progress | 95% Completed | 01/08/2021
95% of work complete except Finishing work
|
Chittur Project Dn - AE 3 |
|