KIIFB - 16-17 - Augmentation of Nenmara, Ayiloor and Melarcode in Chittur and Alathur Taluk in Palakkad District- Phase II-

Project KIIFB - 16-17 - Augmentation of Nenmara, Ayiloor and Melarcode in Chittur and Alathur Taluk in Palakkad District- Phase II-
Project Code PKDKIIFB1117627
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description This project is for augmentation of the existing water supply scheme to Nenmara, Ayilur and Melarcode Panchayaths in Chittur and Alathur taluk. For the coverage of all habitations of three Panchayaths by utilizing perennial surface source of Pothundi irrigation Dam in Nemmara panchayath. The Package I and Package II is an ongoing project under WSP Project Division, Palakkad. The construction of 11.50 LL OHSR with staging height 3metre included in the Package I along with the laying of 450 mm DI K9 distribution main for a length of 1900m. The laying of distribution main completed. During the soil investigation work for the construction of OHSR it is seen that the site is unsuitable for the construction on removal of the boulders found at the site and site clearance. Hence alternate suitable land identified . . The component of 11.50 LL OHSR separately arranged as the contractor not carried out the construction of OHSR.
Status Completed
District Palakkad
Executing Office Chittur Project Dn
AS Amount (Rs) 245000000
AS Number GO(Rt) no 14/2017/WRD dtd 11.01.2017
TS Amount (Rs)
TS Number TS/2019-2020/2018/12947
Total Bill Submitted (Rs) 89314886
Total Bill Paid (Rs) 89314886
Population Benefitted 131659
Capacity in MLD 12.00
Actual Project Completion Date 09 May 2021
Coverage 70 lpcd ,Nemmara Ayilur Melarcode Grama panchayaths
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB - 2016 - 2017 Augmentation of WSS to Nemmara,Ayilur and Melarcode panchayaths Phase-II-Package II- Balance work of supplying, Laying, Testing, Commissioning and maintenance of Clear water Pumping main,Distribution lines for Ayilur and Melarcode Zones and balance works of 9.50LL OHSR at Kadampidi in Melarcode Panchayath Project Division Chittur
2 Project Division Chittur KIIFB - 16-17 - Augmentation of Nenmara, Ayiloor and Melarcode in Chittur and Alathur Taluk in Palakkad District- Phase II- Package I - Design, construction and commissioning of 11.5 LL OHSR , RCC retaining wall including compound wall at Kaithachira in Ayiloor panchayath - Part 1 Project Division Chittur

Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Mar 2023 Pack-1 Work of OHSR has been completed 100%-on 17.03.2022 Pack-2-balance work- Work has been completed | 100% Completed | 31/03/2023 work completed on 28.01.2023 Chittur Project Dn - AE 3
24 Mar 2023 Work in progress | 98% Completed | 24/03/2023 pack-2-KIIFb-leak rectification work in progress,painting work completed,linking works are also balance Chittur Project Dn - AE 3
05 Mar 2023 Work in progress | 98% Completed | 05/03/2023 pack-2-KIIFb-leak rectification work in progress,painting work completed,linking works are also balance Chittur Project Dn - AE 3
24 Feb 2023 Work in progress | 98% Completed | 24/02/2023 pack-2-KIIFb-leak rectification work in progress,painting work completed,linking works are also balance Chittur Project Dn - AE 3
17 Feb 2023 Work in progress | 98% Completed | 17/02/2023 pack-2-KIIFb-leak rectification work in progress,painting work completed,linking works are also balance Chittur Project Dn - AE 3

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 11/10/2019
Scheduled date of Completion of the Project 09 May 2021
Expected date of Completion 28/02/2023

Processing Dates

AS Date 11 Jan 2017
TS Date 12 Jun 2019

Other details

Project Officers View