Status Date Overall Project Status Project Officer Contact
12 Dec 2021 Pack-2 Work in progress | 80% Completed | 12/12/2021 Basement filling work in progress 1).Pumping main and distribution linking works are almost complete 2).Compound wall -belt work in progress Pack-1 Work in progress | 95% Completed | 12/12/2021 95% of work complete except Finishing work, Chittur Project Dn - AE 3
05 Dec 2021 Phase-2-pack-2 Work in progress | 80% Completed | 05/12/2021 basement filling work in progress 1).Pumping main and distribution linking works are almost complete 2).Compound wall -belt work in progress phase-2-pack-1 Work in progress | 95% Completed | 05/12/2021 95% of work complete except Finishing work, letter submitted to contractor for completing the work urgently Chittur Project Dn - AE 3
28 Nov 2021 Pack-1 Work in progress | 95% Completed | 28/11/2021 95% of work complete except Finishing work, letter submitted to contractor for completing the work urgently. Part-2 Work in progress | 80% Completed | 28/11/2021 basement filling work in progress 1).Pumping main and distribution linking works are almost complete 2).Compound wall -foundation work in progress Chittur Project Dn - AE 3
21 Nov 2021 Ph-2-pack-2 Work in progress | 80% Completed | 21/11/2021 basement filling work in progress 1).Pumping main and distribution linking works are almost complete 2).Compound wall work is to be done, compound wall and gate design submitted to SE office for approval on 29.10.2021 ph-2-pack-1 Work in progress | 95% Completed | 21/11/2021 95% of work complete except Finishing work, letter submitted to contractor for completing the work urgently. Chittur Project Dn - AE 3
14 Nov 2021 Pack-2 Work in progress | 80% Completed | 14/11/2021 basement filling work in progress 1).Pumping main and distribution linking works are almost complete 2).Compound wall work is to be done, compound wall and gate design submitted to SE office for approval on 29.10.2021 pack-1 Work in progress | 95% Completed | 14/11/2021 95% of work complete except Finishing work, letter submitted to contractor for completing the work urgently. Chittur Project Dn - AE 3
07 Nov 2021 Pack-1 Work in progress | 95% Completed | 07/11/2021 95% of work complete except Finishing work, letter submitted to contractor for completing the work urgently. Pack-2 Work in progress | 80% Completed | 07/11/2021 basement filling work in progress 1).Pumping main and distribution linking works are almost complete 2).Compound wall work is to be done, compound wall and gate design submitted to SE office for approval on 29.10.2021 Chittur Project Dn - AE 3
31 Oct 2021 Pack-2 Work in progress | 77% Completed | 31/10/2021 1).Pumping main and distribution linking works are almost complete 2).Compound wall work is to be done, compound wall and gate design submitted to SE office for approval on 29.10.2021 Pack-1 Work in progress | 95% Completed | 31/10/2021 95% of work complete except Finishing work, letter submitted to contractor for completing the work urgently. Chittur Project Dn - AE 3
24 Oct 2021 Pack-2 Work in progress | 77% Completed | 24/10/2021 1).Pumping main and distribution linking works are almost complete 2).Compound wall work is to be done Pack-1 Work in progress | 95% Completed | 24/10/2021 95% of work complete except Finishing work Chittur Project Dn - AE 3
17 Oct 2021 Pack-1 Work in progress | 95% Completed | 17/10/2021 95% of work complete except Finishing work Pack-2 Work in progress | 77% Completed | 17/10/2021 1).Pumping main and distribution linking works are almost complete 2).Compound wall work is to be done Chittur Project Dn - AE 3
10 Oct 2021 Pack-1 Work in progress | 95% Completed | 10/10/2021 95% of work complete except Finishing work Pack-2 Work in progress | 77% Completed | 10/10/2021 1. Pumping main and distribution linking works are in progress 2. Compound wall work is to be done 3. Column pipe work in progress Chittur Project Dn - AE 3