Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
31 Mar 2022 | Pack-1-completed Pack-2 Work in progress | 95% Completed | 31/03/2022 Approach road concrete work is in progress | Chittur Project Dn - AE 3 | |
23 Mar 2022 | Pack-1 Work has been completed | 100% Completed | 17/03/2022 Work of OHSR has been completed PACK-2 Work in progress | 95% Completed | 23/03/2022 Work of OHSR has been completed and distribution lines charged. water supply to consumers is being done partially. 900 m pipeline laying is balance since PWD permission is not obtained. | Chittur Project Dn - AE 3 | |
17 Mar 2022 | Pack-2 Work in progress | 95% Completed | 17/03/2022 Work of OHSR has been completed and distribution lines charged. water supply to consumers is being done partially. 900 m pipeline laying is balance since PWD permission is not obtained. Pack-1 Work has been completed | 100% Completed | 17/03/2022 Work of OHSR has been completed | Chittur Project Dn - AE 3 | |
16 Mar 2022 | Pack-2 Work in progress | 91% Completed | 16/03/2022 work under finishing stage PACK-1 Work in progress | 97% Completed | 16/03/2022 water filling work in progress | Chittur Project Dn - AE 3 | |
15 Mar 2022 | Pack-2 Work in progress | 91% Completed | 15/03/2022 work under finishing stage PACK-1 Work in progress | 97% Completed | 15/03/2022 water filling work in progress | Chittur Project Dn - AE 3 | |
10 Mar 2022 | Pack-1 Work in progress | 96% Completed | 10/03/2022 water filling work in progress Pack-2 Work in progress | 91% Completed | 10/03/2022 Compound wall plastering work in progress | Chittur Project Dn - AE 3 | |
03 Mar 2022 | Pack-1 Work in progress | 96% Completed | 03/03/2022 water filling work in progress pack-2 Work in progress | 90% Completed | 03/03/022 Compound wall plastering work in progress | Chittur Project Dn - AE 3 | |
22 Feb 2022 | Pack-1 Work in progress | 96% Completed | 22/02/2022 water filling work in progress pack-2 Work in progress | 90% Completed | 22/02/2022 Compound wall brick work &plastering work in progress | Chittur Project Dn - AE 3 | |
14 Feb 2022 | Pack-1 Work in progress | 95% Completed | 13/02/2022 95% of work complete except Finishing work Pack-2 Work in progress | 86% Completed | 13/02/2022 Compound wall brick work &plastering work in progress | Chittur Project Dn - AE 3 | |
06 Feb 2022 | Pack-1 Work in progress | 95% Completed | 06/02/2022 95% of work complete except Finishing work Pack-2 Work in progress | 86% Completed | 06/02/2022 Compound wall brick work &plastering work in proges | Chittur Project Dn - AE 3 |