| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 11 Apr 2023 | Agreement executed. LOA issued. Tested pipe & specials not get. | Kollam WS Sn 1 - AE | |
| 11 Apr 2023 | Agreement executed. LOA issued. Tested pipe & specials not get | Kollam WS Sn 2 - AE | |
| 08 Apr 2023 | Agreement executed. LOA issued. Tested pipe & specials not get. | Kollam WS Sn 2 - AE | |
| 04 Apr 2023 | Agreement executed. LOA issued. Tested pipe & specials not get. | Kollam WS Sn 1 - AE | |
| 04 Apr 2023 | Agreement executed. Tested pipe & specials not get. | Kollam WS Sn 2 - AE | |
| 31 Mar 2023 | Agreement executed. | Kollam WS Sn 2 - AE | |
| 30 Mar 2023 | Sakthikulangara & Kollam Muncipal corporation Agreement executed | Kollam PH Dn EE |