| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Jun 2023 | Package 3- Pipe laying works in progress. As the dispute beteween licensed plumbers union, FHTC works temporarily stopped | Kollam WS Sn 2 - AE | |
| 01 Jun 2023 | Package-1:-Beneficiary list received from corporation, Package-2;-PQ Submitted to CE office, Package-3:- 2 % completed and Pipe laying in progress, but from 30/5/23 work interrupted due the dispute between licensed plumbers union. | Kollam WS Sn 2 - AE | |
| 29 May 2023 | Package-1:-Beneficiary list received from corporation, Package-2;-PQ Submitted to CE office, Package-3:- 2 % completed and Pipe laying & FHTC given works in progress | Kollam WS Sn 2 - AE | |
| 24 May 2023 | Package-1:-Beneficiary list received from corporation, Package-2;-PQ Submitted to CE office, Package-3:-Pipe laying & FHTC given works in progress | Kollam WS Sn 2 - AE | |
| 22 May 2023 | Package-1:-Beneficiary list received from corporation,Package-2;-PQ Submitted to CE office,Package-3:-Pipe laying works in progress | Kollam PH Dn EE | |
| 19 May 2023 | package 3- Pipe laying works is in progress | Kollam WS Sn 2 - AE | |
| 17 May 2023 | package3- Work started today | Kollam WS Sn 2 - AE | |
| 15 May 2023 | Package 1- Tested pipe & specials not get Package 2- PQ Submitted to CE office Package 3- tested pipe got, beneficiary list from corporation received , work will start soon. | Kollam WS Sn 2 - AE | |
| 11 May 2023 | Package 1- Tested pipe & specials not get Package 2- PQ Submitted to CE office Package 3- Waiting for tested pipe & specials | Kollam WS Sn 2 - AE | |
| 11 May 2023 | Package 3-Waiting for tested pipe & specials | Kollam WS Sn 2 - AE |