| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 13 Jul 2023 | PAckage-1,Agreement executed on 04.07.2023, PAckage-2,Agreement executed on 07.07.2023, PAckage-3 pipe laying ongoing | Kollam WS Sn 2 - AE | |
| 13 Jul 2023 | PAckage-1,Agreement executed on 04.07.2023, PAckage-2,Agreement executed on 07.07.2023, PAckage-3 pipe laying ongoing | Kollam PH Dn EE | |
| 13 Jul 2023 | Package 3- FHTC given works interrupted by the licensed plumbers union.Sakthikulangara & Thrikkadavoor - Pipe laying works in progress | Kollam PH Dn EE | |
| 04 Jul 2023 | Package 3- FHTC given works interrupted by the licensed plumbers union.Sakthikulangara & Thrikkadavoor - Pipe laying works in progress | Kollam WS Sn 2 - AE | |
| 28 Jun 2023 | Package 3- FHTC given works interrupted by the licensed plumbers union.Sakthikulangara & Thrikkadavoor - Pipe laying works in progress | Kollam WS Sn 2 - AE | |
| 24 Jun 2023 | Package 3- FHTC given works interrupted by the licensed plumbers union.Sakthikulangara & Thrikkadavoor - Pipe laying works continuous | Kollam WS Sn 2 - AE | |
| 20 Jun 2023 | Package 3- FHTC given works interrupted by the licensed plumbers union.Sakthikulangara & Thrikkadavoor - Pipe laying works continuous, heavy rain affects the good progress | Kollam WS Sn 2 - AE | |
| 16 Jun 2023 | Package 3- FHTC given works interrupted by the licensed plumbers union.Sakthikulangara & Thrikkadavoor - Pipe laying works continuous, heavy rain affects the good progress | Kollam WS Sn 2 - AE | |
| 12 Jun 2023 | Package 3- FHTC given works interrupted by the licensed plumbers union.Sakthikulangara & Thrikkadavoor - Pipe laying works continuous, heavy rain affects the good progress | Kollam WS Sn 2 - AE | |
| 09 Jun 2023 | Package 3- Sakthikulangara & Thrikkadavoor - Pipe laying works in progress. FHTC given works interrupted by the licensed plumbers union. | Kollam WS Sn 2 - AE |