Status Date Overall Project Status Project Officer Contact
14 Mar 2024 33.26/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Project Dn EE
13 Mar 2024 33.26/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Project Dn EE
12 Mar 2024 33.26/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Project Dn EE
11 Mar 2024 33.26/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Project Dn EE
09 Mar 2024 33.26/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Project Dn EE
08 Mar 2024 32.97/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Project Dn EE
07 Mar 2024 32.70/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road,Karayur - Vannanthara Road) work progress Palakkad Project Dn EE
06 Mar 2024 32.63/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road,Karayur - Vannanthara Road) work progress Palakkad Project Dn EE
05 Mar 2024 32.63/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road,Karayur - Vannanthara Road) work progress Palakkad Project Dn EE
04 Mar 2024 32.63/91.30 km completed. Remaining PVC, HDPE & DI laying progressing, 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress Palakkad Proj AE 3