Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Mar 2024 | 33.26/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Project Dn EE | |
13 Mar 2024 | 33.26/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Project Dn EE | |
12 Mar 2024 | 33.26/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Project Dn EE | |
11 Mar 2024 | 33.26/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Project Dn EE | |
09 Mar 2024 | 33.26/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Project Dn EE | |
08 Mar 2024 | 32.97/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Project Dn EE | |
07 Mar 2024 | 32.70/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road,Karayur - Vannanthara Road) work progress | Palakkad Project Dn EE | |
06 Mar 2024 | 32.63/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road,Karayur - Vannanthara Road) work progress | Palakkad Project Dn EE | |
05 Mar 2024 | 32.63/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road,Karayur - Vannanthara Road) work progress | Palakkad Project Dn EE | |
04 Mar 2024 | 32.63/91.30 km completed. Remaining PVC, HDPE & DI laying progressing, 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 |