Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
20 Apr 2024 | 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
19 Apr 2024 | 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
18 Apr 2024 | 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
15 Apr 2024 | 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
11 Apr 2024 | 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
09 Apr 2024 | 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
08 Apr 2024 | 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
05 Apr 2024 | 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
03 Apr 2024 | 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
02 Apr 2024 | 34.54/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 |