Status Date Overall Project Status Project Officer Contact
17 May 2024 35.49/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3
16 May 2024 35.49/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3
15 May 2024 35.46/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3
14 May 2024 35.41/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3
13 May 2024 35.41/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3
10 May 2024 35.41/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3
09 May 2024 35.35/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3
08 May 2024 35.35/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3
07 May 2024 35.29/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3
06 May 2024 35.24/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3