Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
17 May 2024 | 35.49/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
16 May 2024 | 35.49/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
15 May 2024 | 35.46/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
14 May 2024 | 35.41/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
13 May 2024 | 35.41/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
10 May 2024 | 35.41/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
09 May 2024 | 35.35/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
08 May 2024 | 35.35/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
07 May 2024 | 35.29/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
06 May 2024 | 35.24/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 |