Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 May 2024 35.16/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3
02 May 2024 35.11/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3
01 May 2024 35.11/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3
30 Apr 2024 35.07/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3
29 Apr 2024 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3
27 Apr 2024 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3
25 Apr 2024 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3
24 Apr 2024 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3
23 Apr 2024 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3
22 Apr 2024 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3