Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
03 May 2024 | 35.16/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
02 May 2024 | 35.11/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
01 May 2024 | 35.11/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
30 Apr 2024 | 35.07/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
29 Apr 2024 | 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
27 Apr 2024 | 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
25 Apr 2024 | 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
24 Apr 2024 | 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
23 Apr 2024 | 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
22 Apr 2024 | 35.02/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 |