23 Apr 2024 |
work was short closed at risk and cost of contractor vide No. KWA/PHC/D5/3065/2016 dated 05- 04-2023 of S E, the original work as cancelled and the tender authority has tendered the balance work. But even after retendering twice no offers were received. So the tender was cancelled. During the meeting convened by Ho'ble Minister for transport ,GoK on 25-07- 2023 has directed to tender the balance work immediately after recasting the estimate to three or more reaches under TS power of thee Executive Engineer. estimate was recasted to four parts and out of these four works only one part completed .remaining three parts tendered and no offer received. |
Thiruvananthapuram Project AE6 |
|
15 Feb 2024 |
work was short closed at risk and cost of
contractor vide No.
KWA/PHC/D5/3065/2016 dated 05- 04-2023
of S E, the original work as cancelled and the
tender authority has tendered the balance
work. But even after retendering twice no
offers were received. So the tender was
cancelled. During the meeting convened by
Ho'ble Minister for transport ,GoK on 25-07-
2023 has directed to tender the balance work
immediately after recasting the estimate to
three or more reaches under TS power of
thee Executive Engineer. |
Thiruvananthapuram Project AE6 |
|
14 Feb 2024 |
work completed |
Thiruvananthapuram Project AE7 |
|
25 Jul 2022 |
Out of 3km, 1056m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables.pipe laying work stopped from 23/05/2022 due to monsoon ban.At present, gap works at paaris road near nandavanam going on. |
Thiruvananthapuram Project AE7 |
|
11 Jul 2022 |
Out of 3km, 1002m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables.pipe laying work stopped from 23/05/2022 due to monsoon ban. |
Thiruvananthapuram Project AE7 |
|
13 Jun 2022 |
Out of 3km, 990m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables.pipe laying work stopped from 23/05/2022 due to monsoon ban. |
Thiruvananthapuram Project AE7 |
|
02 Jun 2022 |
Out of 3km, 990m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables.pipe laying work stopped from 23/05/2022 due to monsoon ban. |
Thiruvananthapuram Project AE7 |
|
30 May 2022 |
Out of 3km, 990m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables.pipe laying work stopped from 23/05/2022 due to monsoon ban. |
Thiruvananthapuram Project AE7 |
|
23 May 2022 |
Out of 3km, 990m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables |
Thiruvananthapuram Project AE7 |
|
20 May 2022 |
Out of 3km, 990m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables |
Thiruvananthapuram Project AE7 |
|